812-814 N GENESEE AVE 90046

Certificate Information: 812-814 N GENESEE AVE 90046

Application / Permit
25010-20000-03894
Plan Check / Job No.
B25VN24802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMOVE ALL EXTERIOR WALL AND INTERIOR WALLS OF AN EXISTING DUPLEX EXCEPT 2.25 LF AT NORTH PORTION OF THE LOT AND BUILD 2-STORY DUPLEX AND ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/22/2025
Issuing Office
Current Status
Issued on 12/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/26/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 RARES BODEA
Assigned to Zoning Architect 8/28/2025 SHARAREH KAHENASSA
Corrections Issued 9/5/2025 RARES BODEA
Quality Review Completed 9/10/2025 STEVEN KIM
Building Plans Picked Up 9/11/2025 APPLICANT
Applicant returned to address corrections 11/14/2025 RARES BODEA
Plan Check Approved 12/22/2025 RARES BODEA
Issued 12/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/23/2025 CARLOS AGUILERA
Sewer availability Cleared 9/23/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/25/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/6/2025 GILBERT URREA
Permit Cleared 12/4/2025 ABEL CASILLAS
Trees in Parkway Cleared 12/4/2025 PEDRO ZUNIGA
Frnt yard landscape/Water mgmt Cleared 12/16/2025 MAIRA SANCHEZ
Zoning Plan Check Cleared 12/17/2025 SHARAREH KAHENASSA
Roof/Waste drainage to street Cleared 12/22/2025 TONY CHIANG

Contact Information

Contractor Owner-Builder       ,
Engineer Amar,, David; Lic. No.: C97582 6160 CORBIN AVENUE      TARZANA, CA 91356

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/21/2026 Partial Approval JOSH MEISTER
Excavation/Setback/Form/Re-Bar 1/23/2026 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/30/2026 Approved JOSH MEISTER
Masonry Wall/Backfill 2/10/2026 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Partial Approval JOSH MEISTER
Green Building Rough 2/17/2026 Not Ready for Inspection JOSH MEISTER
Masonry Wall/Backfill 2/17/2026 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Corrections Issued JOSH MEISTER
PLUMBING-Rough 3/27/2026 Not Ready for Inspection JOSH MEISTER
ELECTRICAL-Rough 4/1/2026 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Approved JOSH MEISTER
HVAC-Rough 4/1/2026 Not Ready for Inspection JOSH MEISTER
PLUMBING-Rough 4/1/2026 Approved JOSH MEISTER
Shower Pan 4/1/2026 Approved JOSH MEISTER
BUILDING-Rough-Frame 4/8/2026 Approved JOSH MEISTER
Green Building Rough 4/8/2026 Not Ready for Inspection JOSH MEISTER
HVAC-Rough 4/8/2026 Approved JOSH MEISTER
Interior/Exterior Lathing 4/8/2026 Partial Approval JOSH MEISTER
Green Building Rough 4/15/2026 Approved JOSH MEISTER
Insulation 4/15/2026 Approved JOSH MEISTER
Interior/Exterior Lathing 4/15/2026 Approved JOSH MEISTER
Drywall Nailing 4/27/2026 Approved JOSH MEISTER