812-814 N GENESEE AVE 90046
Certificate Information: 812-814 N GENESEE AVE 90046
- Application / Permit
- 25010-20000-03894
- Plan Check / Job No.
- B25VN24802
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMOVE ALL EXTERIOR WALL AND INTERIOR WALLS OF AN EXISTING DUPLEX EXCEPT 2.25 LF AT NORTH PORTION OF THE LOT AND BUILD 2-STORY DUPLEX AND ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/22/2025
- Issuing Office
- Current Status
- Issued on 12/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2025 | RARES BODEA |
| Assigned to Zoning Architect | 8/28/2025 | SHARAREH KAHENASSA |
| Corrections Issued | 9/5/2025 | RARES BODEA |
| Quality Review Completed | 9/10/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/11/2025 | APPLICANT |
| Applicant returned to address corrections | 11/14/2025 | RARES BODEA |
| Plan Check Approved | 12/22/2025 | RARES BODEA |
| Issued | 12/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/23/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/6/2025 | GILBERT URREA |
| Permit | Cleared | 12/4/2025 | ABEL CASILLAS |
| Trees in Parkway | Cleared | 12/4/2025 | PEDRO ZUNIGA |
| Frnt yard landscape/Water mgmt | Cleared | 12/16/2025 | MAIRA SANCHEZ |
| Zoning Plan Check | Cleared | 12/17/2025 | SHARAREH KAHENASSA |
| Roof/Waste drainage to street | Cleared | 12/22/2025 | TONY CHIANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Amar,, David; Lic. No.: C97582 | 6160 CORBIN AVENUE TARZANA, CA 91356 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/21/2026 | Partial Approval | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 1/23/2026 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/30/2026 | Approved | JOSH MEISTER |
| Masonry Wall/Backfill | 2/10/2026 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2026 | Partial Approval | JOSH MEISTER |
| Green Building Rough | 2/17/2026 | Not Ready for Inspection | JOSH MEISTER |
| Masonry Wall/Backfill | 2/17/2026 | Approved | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2026 | Corrections Issued | JOSH MEISTER |
| PLUMBING-Rough | 3/27/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Rough | 4/1/2026 | Approved | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Approved | JOSH MEISTER |
| HVAC-Rough | 4/1/2026 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Rough | 4/1/2026 | Approved | JOSH MEISTER |
| Shower Pan | 4/1/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/8/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 4/8/2026 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Rough | 4/8/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/8/2026 | Partial Approval | JOSH MEISTER |
| Green Building Rough | 4/15/2026 | Approved | JOSH MEISTER |
| Insulation | 4/15/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/15/2026 | Approved | JOSH MEISTER |
| Drywall Nailing | 4/27/2026 | Approved | JOSH MEISTER |