5046 N GREENBUSH AVE 91423

Certificate Information: 5046 N GREENBUSH AVE 91423

Application / Permit
25010-20000-03888
Plan Check / Job No.
B25VN24788
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 15' x 17'-6" REC ROOM W/ AN ATT BATHROOM (ACCESS FROM OUTSIDE)
Permit Issued
Issued on 1/7/2026
Issuing Office
Current Status
Issued on 1/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/26/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 SEAN SHAHMIRI
Assigned to Zoning Architect 8/28/2025 RYAN DEL POSO
Corrections Issued 9/8/2025 SEAN SHAHMIRI
Quality Review Completed 9/10/2025 STEVEN KIM
Building Plans Picked Up 9/11/2025 APPLICANT
Applicant returned to address corrections 12/31/2025 SEAN SHAHMIRI
Plan Check Approved 12/31/2025 SEAN SHAHMIRI
No Progress 12/31/2025 SEAN SHAHMIRI
Plan Check Approved 12/31/2025 SEAN SHAHMIRI
Issued 1/7/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/25/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/26/2025 BIAINA HARITUNIAN
ZI Cleared 11/6/2025 DANIEL CORONADO
Construction near power lines Cleared 11/14/2025 WALTER RAMIREZ
Zoning Plan Check Cleared 12/29/2025 RYAN DEL POSO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Drywall Nailing 7/24/2026   

Inspection Request History

PLUMBING-Rough 2/5/2026 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/12/2026 Corrections Issued MISAEL ESPARZA
Wood Frame 3/14/2026 Off-Hour Fees Due
Deputy Reinf. Concrete 3/17/2026 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/17/2026 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 4/29/2026 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 6/8/2026 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/8/2026 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 6/11/2026 Approved MISAEL ESPARZA
PLUMBING-Rough 6/11/2026 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/15/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 6/15/2026 Corrections Issued MISAEL ESPARZA
Wood Frame 6/22/2026 Not Ready for Inspection MISAEL ESPARZA
Insulation 7/10/2026 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 7/10/2026 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/15/2026 Conditional Approval MISAEL ESPARZA
Insulation 7/15/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/15/2026 Partial Approval MISAEL ESPARZA