10157 N BEVIS AVE 91345
Certificate Information: 10157 N BEVIS AVE 91345
- Application / Permit
- 25010-20000-03750
- Plan Check / Job No.
- B25VN23926
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 12' X 25' DETACHED REAR PATIO COVER PER ENGINEERING.
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- Issued on 8/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 8/18/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 8/29/2025 | GIOVANNY CHAVEZ |
| Issued | 8/29/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/19/2025 | EDGAR PASCUA |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/22/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/27/2026 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 1/27/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/10/2026 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 2/10/2026 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/2/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/27/2026 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 3/27/2026 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/28/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/28/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/7/2026 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/7/2026 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/7/2026 | Approved | JENNIFER RABUCHIN |