5646 N ANDASOL AVE 91316
Certificate Information: 5646 N ANDASOL AVE 91316
- Application / Permit
- 25010-20000-03740
- Plan Check / Job No.
- B25VN23884
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-0" X 25'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 8/23/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/26/2025 | APPLICANT |
| Plan Check Approved | 9/8/2025 | OMAR GARNICA |
| Issued | 9/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 8/27/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 8/28/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 1038 FLANDERS RD LA CANADA-FLNTRDG, CA 91011 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/1/2025 | Partial Approval | MORRIS JACKSON |
| Underground Mechanical | 10/1/2025 | Partial Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/7/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | No Access for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 10/31/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Final | 10/31/2025 | Corrections Issued | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 11/4/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 11/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 11/4/2025 | Approved | MORRIS JACKSON |
| MERV13>=Rough | 11/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 11/4/2025 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 11/4/2025 | Partial Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/7/2025 | Corrections Issued | SEAN WIRCH |
| BUILDING-Rough-Frame | 11/26/2025 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/26/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | JON MCHUGH |
| Green Building Rough | 12/2/2025 | Approved | JON MCHUGH |
| Insulation | 12/2/2025 | Conditional Approval | JON MCHUGH |
| MERV13>=Rough | 12/2/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 12/2/2025 | Approved | JON MCHUGH |
| Insulation | 12/4/2025 | Approved | MORRIS JACKSON |
| Pre-Inspection | 12/4/2025 | Partial Inspection | MORRIS JACKSON |
| Drywall Nailing | 12/8/2025 | Approved | MORRIS JACKSON |
| Final | 4/2/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 4/2/2026 | Approved | MORRIS JACKSON |
| MERV13>=Final | 4/2/2026 | Not Ready for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Not Ready | MORRIS JACKSON |
| Service/Power Release | 4/2/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Smoke Detectors | 4/2/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 4/15/2026 | Partial Inspection | MORRIS JACKSON |
| MERV13>=Final | 4/15/2026 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 4/15/2026 | Approved | MORRIS JACKSON |
| Smoke Detectors | 4/15/2026 | Approved | MORRIS JACKSON |
| Final | 4/23/2026 | Corrections Issued | MORRIS JACKSON |