14079 W DAUBERT ST 91340

Certificate Information: 14079 W DAUBERT ST 91340

Application / Permit
25010-20000-03686
Plan Check / Job No.
B25VN23582
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/22/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2025 APPLICANT
Assigned to Plan Check Engineer 8/21/2025 JEROME MAGAT PALMA
Corrections Issued 8/22/2025 JEROME MAGAT PALMA
Building Plans Picked Up 8/28/2025 APPLICANT
Plan Check Approved 9/22/2025 OMAR GARNICA
Issued 9/22/2025 APPLICANT
CofO in Progress 5/1/2026 JENNIFER RABUCHIN
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/5/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/5/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 9/5/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/5/2025 SAFA JAVANMARDI

Contact Information

Contractor Valenzuela Pancho Construction; Lic. No.: 1067736-B 544 ORANGE GROVE AVE      SAN FERNANDO, CA 91340

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2025 Approved JENNIFER RABUCHIN
METHANE-Barrier 10/23/2025 Approved JENNIFER RABUCHIN
METHANE-Subgrade 10/23/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/4/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 11/4/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Partial Approval JENNIFER RABUCHIN
Insulation 11/6/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/2/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/2/2025 Approved JENNIFER RABUCHIN
Green Building Rough 12/2/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 12/2/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/2/2025 Partial Approval JENNIFER RABUCHIN
METHANE-Rough 12/2/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/2/2025 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/2/2025 Approved JENNIFER RABUCHIN
Insulation 12/4/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 12/9/2025 Approved CHRISTOPHER MORFIN
Shower Pan 12/9/2025 Approved CHRISTOPHER MORFIN
Interior/Exterior Lathing 12/12/2025 Approved JENNIFER RABUCHIN
Sewer 12/12/2025 Approved JENNIFER RABUCHIN
Final 4/23/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/23/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 4/23/2026 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 4/23/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/1/2026 Approved JENNIFER RABUCHIN
Final 5/1/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/1/2026 Approved JENNIFER RABUCHIN
HVAC-Final 5/1/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/1/2026 Approved JENNIFER RABUCHIN
Service/Power Release 5/1/2026 Approved JENNIFER RABUCHIN