18798 W LULL ST 91335

Certificate Information: 18798 W LULL ST 91335

Application / Permit
25010-20000-03665
Plan Check / Job No.
B25VN23380
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 47'-0" X 33'-9" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT W/PORCH PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 9/12/2025
Issuing Office
Current Status
Issued on 9/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2025 APPLICANT
Assigned to Plan Check Engineer 8/20/2025 ARTIN ZARUKIAN
Corrections Issued 8/20/2025 ARTIN ZARUKIAN
Building Plans Picked Up 8/25/2025 APPLICANT
Plan Check Approved 9/5/2025 YAQUB MIRZA
Plan Check Approved 9/5/2025 YAQUB MIRZA
Issued 9/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/29/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 8/29/2025 DERRICK MAGEE
Miscellaneous Cleared 8/29/2025 ASHLEY RODARTE
Miscellaneous Cleared 8/29/2025 ASHLEY RODARTE
Roof/Waste drainage to street Cleared 8/29/2025 DERRICK MAGEE
Sewer availability Cleared 8/29/2025 DERRICK MAGEE
ZA Case Cleared 8/29/2025 ASHLEY RODARTE
ZI Cleared 8/29/2025 ASHLEY RODARTE

Contact Information

Contractor Vision Adu Llc; Lic. No.: 1115842-B 405 S MISSION DR      SAN GABRIEL, CA 91776
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/29/2025 Corrections Issued KRISTEN CAUSEY
PLUMBING-Rough 9/29/2025 Partial Approval KRISTEN CAUSEY
Footing/Foundation/Slab 10/10/2025 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 10/21/2025 Not Ready for Inspection JUAN ALVARADO
Footing/Foundation/Slab 10/21/2025 Not Ready for Inspection JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 10/23/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 10/23/2025 Approved JUAN ALVARADO
Structural Steel Frame 10/23/2025 No Access for Inspection JUAN ALVARADO
ELECTRICAL-Rough 12/1/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Approved JUAN ALVARADO
Green Building Rough 12/1/2025 Not Ready for Inspection JUAN ALVARADO
HVAC-Rough 12/1/2025 Approved JUAN ALVARADO
PLUMBING-Rough 12/1/2025 Corrections Issued JUAN ALVARADO
Verify Sprinkler Sign Off 12/1/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 12/4/2025 Approved JUAN ALVARADO
HVAC-Rough 12/4/2025 Approved JUAN ALVARADO
PLUMBING-Rough 12/4/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 12/8/2025 Approved JUAN ALVARADO
Green Building Rough 12/8/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 12/8/2025 Approved JUAN ALVARADO
Insulation 12/11/2025 Approved JEFFREY HARTLINE
Drywall Nailing 12/16/2025 Approved JUAN ALVARADO
Sewer 12/29/2025 Corrections Issued JUAN ALVARADO
Underground Mechanical 1/12/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 2/11/2026 Corrections Issued JUAN ALVARADO
Service/Power Release 2/25/2026 Not Ready for Inspection JUAN ALVARADO
Underground Mechanical 2/25/2026 Approved JUAN ALVARADO
Service/Power Release 3/18/2026 Not Ready for Inspection JUAN ALVARADO