1919 S CENTRAL AVE 1-5 90011

Certificate Information: 1919 S CENTRAL AVE 1-5 90011

Application / Permit
25010-20000-03581
Plan Check / Job No.
B25VN22853
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY APARTMENT BUILDING AT THE REAR ( FIVE ADUS PER GC & 66323(a)(4)
Permit Issued
Issued on 3/27/2026
Issuing Office
Current Status
Issued on 3/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/7/2025 APPLICANT
Assigned to Zoning Architect 8/7/2025 ELAHE MERRIKHI
Assigned to Plan Check Engineer 8/14/2025 SERGIO GUTIERREZ
Corrections Issued 8/18/2025 SERGIO GUTIERREZ
Quality Review Completed 8/22/2025 PRANITA SHAH
Applicant returned to address corrections 1/22/2026 SERGIO GUTIERREZ
Applicant returned to address corrections 2/11/2026 SERGIO GUTIERREZ
Plan Check Approved 3/27/2026 SERGIO GUTIERREZ
Issued 3/27/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/23/2025 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/23/2025 ABEL CASILLAS
Sewer availability Cleared 10/23/2025 ABEL CASILLAS
Hydrant and Access approval Cleared 10/29/2025 PATRICK PEREZ
DAS Clearance Cleared 10/31/2025 NORLITO MEDRANO
Green Code Cleared 10/31/2025 MICHAEL AYERS
Roof/Waste drainage to street Cleared 11/4/2025 MICHAEL BROWN
ZA Case Cleared 11/12/2025 ANGELA WILLIAMS
Historic Resource Verification Cleared 11/25/2025 LAMBERT GIESSINGER
Community Plan Implem. Overlay Cleared 12/12/2025 STEVE GARCIA
Redevelopment Project Area Cleared 1/5/2026 YASMINE BASHIRI
Zoning Plan Check Cleared 3/16/2026 ELAHE MERRIKHI

Contact Information

Contractor Adu Express Construction Llc; Lic. No.: 1035634-B       ,
Contractor Arash Mofakham; Lic. No.: 1035634-B       ,
Engineer Aalam,, Yahya; Lic. No.: C94318 3111 4TH ST APT 401      SANTA MONICA, CA 90405

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2026 Corrections Issued JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 5/12/2026 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 5/12/2026 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2026 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/18/2026 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2026 Corrections Issued JOEY BUCHANAN