1048 N VILLA GROVE DR 90272

Certificate Information: 1048 N VILLA GROVE DR 90272

Application / Permit
25010-20000-03440
Plan Check / Job No.
B25VN22027
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 46'-4.5" X 87'-6.5". NFPA 13D SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/28/2026
Issuing Office
Current Status
Issued on 1/28/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 RAPHAEL ROSAS
Corrections Issued 8/6/2025 RAPHAEL ROSAS
Quality Review Completed 8/6/2025 STEVEN KIM
Building Plans Picked Up 8/6/2025 APPLICANT
Applicant returned to address corrections 8/26/2025 RAPHAEL ROSAS
Plan Check Approved 9/5/2025 RAPHAEL ROSAS
Issued 1/28/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/5/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/5/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/5/2025 SAFA JAVANMARDI
Permit Cleared 8/6/2025 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 8/11/2025 JOHN CONNEALLY

Contact Information

Contractor Stephenson C & Sons Inc; Lic. No.: 835159-B 3841 OLD CONEJO RD      NEWBURY PARK, CA 91320
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Tani,, Jason; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Deputy Wood Construction 7/24/2026   

Inspection Request History

PLUMBING-Rough 3/16/2026 Approved HERBERT GIRON
Footing/Foundation/Slab 3/18/2026 Partial Approval MICHAEL ALLEN
Deputy Reinf. Concrete 3/20/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 3/27/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/1/2026 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 4/1/2026 Corrections Issued TEMISTOCLES CAAL
Grounding or Bonding 4/1/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 5/20/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/21/2026 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 5/21/2026 Approved TEMISTOCLES CAAL
Sewer 6/9/2026 Approved TEMISTOCLES CAAL
Underground Mechanical 6/9/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 6/18/2026 Approved TEMISTOCLES CAAL
Shower Pan 6/18/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 6/26/2026 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 6/29/2026 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 7/13/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 7/13/2026 Approved TEMISTOCLES CAAL
Green Building Rough 7/13/2026 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 7/13/2026 Approved TEMISTOCLES CAAL
Insulation 7/23/2026 Conditional Approval ARAM AVEDISIAN
Insulation 7/24/2026 Approved ARAM AVEDISIAN