14968 W GREENLEAF ST 91403
Certificate Information: 14968 W GREENLEAF ST 91403
- Application / Permit
- 25010-20000-03399
- Plan Check / Job No.
- B25VN21764
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD W/ ATTACHED TWO GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/11/2025
- Issuing Office
- Current Status
- Issued on 9/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | RARES BODEA |
| Assigned to Zoning Architect | 7/31/2025 | KAITA SAITO |
| Corrections Issued | 8/8/2025 | RARES BODEA |
| Quality Review Completed | 8/11/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 8/12/2025 | APPLICANT |
| Applicant returned to address corrections | 9/2/2025 | RARES BODEA |
| Plan Check Approved | 9/11/2025 | RARES BODEA |
| Issued | 9/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 8/7/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 8/7/2025 | MICHAEL BROWN |
| Low Impact Development (LID) | Cleared | 8/13/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 8/24/2025 | PATRICK PEREZ |
| GPI Written Notices | Cleared | 9/2/2025 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 9/2/2025 | RARES BODEA |
| Zoning Plan Check | Cleared | 9/5/2025 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 9/18/2025 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 9/22/2025 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/29/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 10/7/2025 | Partial Inspection | MISAEL ESPARZA |
| Deputy Steel/Welding | 10/31/2025 | Conditional Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/12/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 11/12/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 11/21/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/4/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 12/4/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/4/2025 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 12/4/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 12/4/2025 | Approved | JACK KARGODORIAN |
| Insulation | 12/9/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 12/9/2025 | Approved | JACK KARGODORIAN |
| Insulation | 12/10/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 12/17/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 2/10/2026 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/22/2026 | Corrections Issued | MICHAEL CORTEZ |
| Footing/Foundation/Slab | 4/22/2026 | Approved | MICHAEL CORTEZ |
| Smoke Detectors | 4/22/2026 | Corrections Issued | MICHAEL CORTEZ |
| ELECTRICAL-Final | 4/27/2026 | Approved | MICHAEL CORTEZ |
| Gas Test | 4/27/2026 | Partial Approval | MICHAEL CORTEZ |
| PLUMBING-Final | 4/27/2026 | Corrections Issued | MICHAEL CORTEZ |
| Gas Test | 4/30/2026 | Approved | MICHAEL CORTEZ |
| PLUMBING-Final | 4/30/2026 | Approved | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Approved | MICHAEL CORTEZ |
| HVAC-Final | 5/5/2026 | Approved | MICHAEL CORTEZ |
| Final | 6/5/2026 | No Result Entered | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/5/2026 | No Result Entered | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 6/5/2026 | No Result Entered | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 6/5/2026 | No Result Entered | ROBERTO PALACIOS-LOPEZ |