14902 W HUBBARD ST 91342
Certificate Information: 14902 W HUBBARD ST 91342
- Application / Permit
- 25010-20000-03398
- Plan Check / Job No.
- B25VN21759
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 8/26/2025
- Issuing Office
- Current Status
- Issued on 8/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2025 | KAMYAR EMAMI |
| Corrections Issued | 8/4/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 8/15/2025 | ISIS ARGUETA |
| Plan Check Approved | 8/25/2025 | ISIS ARGUETA |
| Issued | 8/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/6/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/6/2025 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 8/7/2025 | ALEXANDER HELFER |
| GPI Written Notices | Cleared | 8/25/2025 | KAMYAR EMAMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/13/2026 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/13/2026 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/20/2026 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/20/2026 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 2/18/2026 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 2/18/2026 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 2/26/2026 | Approved Pending GreenApproval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/26/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/26/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 2/26/2026 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 2/26/2026 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 2/26/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/6/2026 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/6/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/11/2026 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/17/2026 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/17/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/23/2026 | Approved | JENNIFER RABUCHIN |
| Sewer | 4/8/2026 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 4/8/2026 | Approved | JENNIFER RABUCHIN |