7345 N LINDLEY AVE 91335

Certificate Information: 7345 N LINDLEY AVE 91335

Application / Permit
25010-20000-03391
Plan Check / Job No.
B25VN21708
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Conversion and addition to existing detached garage to ADU per GC 66323(a)(1)
Permit Issued
Issued on 9/8/2025
Issuing Office
Current Status
Issued on 9/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/30/2025 APPLICANT
Assigned to Plan Check Engineer 8/1/2025 CAROLEAN BASMA
Corrections Issued 8/4/2025 CAROLEAN BASMA
Applicant returned to address corrections 8/28/2025 CAROLEAN BASMA
Plan Check Approved 9/4/2025 JOHNPAUL ISIP
Issued 9/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/14/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/14/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/18/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/20/2025 SAFA JAVANMARDI

Contact Information

Contractor Hexagon Construction; Lic. No.: 1082693-B       ,
Contractor Tke Leadership Inc; Lic. No.: 1082693-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/30/2025 Approved JUAN ALVARADO
Deputy Drilled-In Anchors 10/3/2025 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 10/3/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 10/24/2025 Not Ready for Inspection JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Corrections Issued JUAN ALVARADO
Green Building Rough 10/24/2025 Not Ready for Inspection JUAN ALVARADO
Wood Frame 10/24/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 11/17/2025 Partial Approval JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Approved JUAN ALVARADO
Green Building Rough 11/17/2025 Not Ready for Inspection JUAN ALVARADO
Interior/Exterior Lathing 11/25/2025 Corrections Issued JUAN ALVARADO
ELECTRICAL-Rough 12/2/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 12/2/2025 Approved JUAN ALVARADO
PLUMBING-Rough 12/2/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 12/5/2025 Approved JUAN ALVARADO
Green Building Rough 12/5/2025 Approved JUAN ALVARADO
HVAC-Rough 12/5/2025 Approved JUAN ALVARADO
Insulation 12/9/2025 Approved JUAN ALVARADO
Underground Mechanical 12/12/2025 Approved JUAN ALVARADO
Drywall Nailing 12/17/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 12/17/2025 Approved JUAN ALVARADO
Shower Pan 12/17/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 12/22/2025 Approved JUAN ALVARADO