11053 N YOLANDA AVE 91326

Certificate Information: 11053 N YOLANDA AVE 91326

Application / Permit
25010-20000-03298
Plan Check / Job No.
B25VN21234
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 12/8/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2025 APPLICANT
Assigned to Plan Check Engineer 7/29/2025 JESSE ARELLANO
Corrections Issued 7/30/2025 JESSE ARELLANO
Building Plans Picked Up 8/4/2025 APPLICANT
Applicant returned to address corrections 9/23/2025 ISIS ARGUETA
Plan Check Approved 11/17/2025 HAYATO TSUCHIYA
Issued 12/8/2025 APPLICANT
CofO in Progress 4/2/2026 DAVID SCANTLIN
Permit Finaled 4/7/2026 JOHN JANSON
CofO Issued 4/7/2026 JOHN JANSON
Permit Finaled 4/7/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/8/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 8/8/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/13/2025 TAL SHEMEN
Sewer availability Cleared 8/13/2025 TAL SHEMEN
Flood clearance Cleared 8/21/2025 ELYSE GREPO
Construction near power lines Cleared 10/15/2025 GEVORK KARAPETYAN

Contact Information

Contractor S & T Builders; Lic. No.: 1090121-B 20729 ENADIA WAY      WINNETKA, CA 91306
Engineer Basma,, Ali J; Lic. No.: C53080 5140 YOLANDA AVE      TARZANA, CA 91356

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/10/2025 Not Ready for Inspection DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 12/23/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 12/23/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 12/30/2025 Approved DAVID SCANTLIN
Deputy Wood Construction 1/12/2026 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 1/26/2026 Approved DAVID SCANTLIN
ELECTRICAL-Rough 1/26/2026 Approved DAVID SCANTLIN
FLOOD-Proofing Certificate 1/26/2026 Approved DAVID SCANTLIN
Green Building Rough 1/26/2026 Approved DAVID SCANTLIN
HVAC-Rough 1/26/2026 Approved DAVID SCANTLIN
PLUMBING-Rough 1/26/2026 Approved DAVID SCANTLIN
Shower Pan 1/26/2026 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 1/26/2026 Approved DAVID SCANTLIN
Insulation 1/29/2026 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 1/29/2026 Partial Approval DAVID SCANTLIN
Drywall Nailing 2/2/2026 Approved DAVID SCANTLIN
Insulation 2/2/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 2/2/2026 Approved DAVID SCANTLIN
Final 3/20/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 3/20/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Approved JACK KARGODORIAN
Service/Power Release 3/20/2026 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 3/20/2026 Approved JACK KARGODORIAN
Final 3/25/2026 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 3/25/2026 Not Ready for Inspection DAVID SCANTLIN
Final 4/2/2026 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 4/2/2026 Approved DAVID SCANTLIN