4523 N KATHERINE AVE 91423

Certificate Information: 4523 N KATHERINE AVE 91423

Application / Permit
25010-20000-03286
Plan Check / Job No.
B25VN21177
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 1-STORY CABANA/REC RM W/ FULL BATH (EXTERIOR ACCESS ONLY FOR POOL UNDER PERMIT NO. 25047-20000-01084
Permit Issued
Issued on 9/16/2025
Issuing Office
Current Status
Issued on 9/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 NILOOFAR MEHRAIN
Corrections Issued 8/7/2025 NILOOFAR MEHRAIN
Quality Review Completed 8/8/2025 JASON HEALEY
Building Plans Picked Up 8/11/2025 APPLICANT
Applicant returned to address corrections 9/2/2025 NILOOFAR MEHRAIN
Plan Check Approved 9/16/2025 NILOOFAR MEHRAIN
Issued 9/16/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/13/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/13/2025 SAFA JAVANMARDI
Construction near power lines Cleared 8/21/2025 ENRIQUE ACOSTA
Construction within easement Cleared 8/21/2025 ENRIQUE ACOSTA
ZI Cleared 9/2/2025 YINGSHI HUANG

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/7/2025 Corrections Issued MISAEL ESPARZA
Sewer 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/8/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/10/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 10/10/2025 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/16/2025 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/20/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/17/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/17/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/19/2025 Approved JACK KARGODORIAN
HVAC-Rough 12/19/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 12/19/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/24/2025 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 12/24/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 12/24/2025 Approved MISAEL ESPARZA
Shower Pan 1/2/2026 Approved MISAEL ESPARZA
Drywall Nailing 1/6/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/6/2026 Approved MISAEL ESPARZA