7331 N VANALDEN AVE 91335
Certificate Information: 7331 N VANALDEN AVE 91335
- Application / Permit
- 25010-20000-03253
- Plan Check / Job No.
- B25VN20906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 31' x 40' DWELLING UNIT PER SB9; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 10/10/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | SEAN SHAHMIRI |
| Corrections Issued | 8/18/2025 | SEAN SHAHMIRI |
| Quality Review Completed | 8/19/2025 | STEVEN KIM |
| Building Plans Picked Up | 8/20/2025 | APPLICANT |
| Applicant returned to address corrections | 10/10/2025 | SEAN SHAHMIRI |
| Plan Check Approved | 10/10/2025 | SEAN SHAHMIRI |
| Issued | 10/10/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | ARUTYUN MADATYAN |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/25/2025 | JEANIE LAM |
| Sewer availability | Cleared | 8/25/2025 | JEANIE LAM |
| Senate Bill 9 | Cleared | 9/16/2025 | JACQUELINE TORRES |
| Construction near power lines | Cleared | 9/19/2025 | GEVORK KARAPETYAN |
| Hydrant and Access approval | Cleared | 10/6/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Goresh Inc; Lic. No.: 1104743-B | 19152 ARCHWOOD ST RESEDA, CA 91335 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2025 | Partial Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/28/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 10/28/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 11/4/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Gas Test | 11/4/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 11/6/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/2/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 12/10/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 12/15/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 12/19/2025 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Approved | ROBERT GOLD |
| Wood Frame | 12/19/2025 | Approved | ROBERT GOLD |
| Shower Pan | 12/26/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Final | 3/18/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 3/18/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 3/18/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 3/18/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 5/7/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 5/7/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 5/7/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/12/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/12/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/12/2026 | Approved | ARUTYUN MADATYAN |