13509 W EBELL ST 91402

Certificate Information: 13509 W EBELL ST 91402

Application / Permit
25010-20000-03146
Plan Check / Job No.
B25VN20198
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 33' 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/28/2025
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 RAPHAEL ROSAS
Corrections Issued 8/6/2025 RAPHAEL ROSAS
Quality Review Completed 8/8/2025 STEVEN KIM
Building Plans Picked Up 8/14/2025 APPLICANT
Plan Check Approved 8/28/2025 RAPHAEL ROSAS
Issued 8/28/2025 APPLICANT
CofO in Progress 3/5/2026 OGANES TARAKHCHYAN
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/7/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 8/18/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 8/18/2025 LEE GUILBEAUX
Sewer availability Cleared 8/18/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 12/10/2025 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/16/2025 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 12/19/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/6/2026 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/6/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 1/6/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 1/6/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/6/2026 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 1/6/2026 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 1/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 1/9/2026 Approved OGANES TARAKHCHYAN
Shower Pan 1/9/2026 Approved OGANES TARAKHCHYAN
Drywall Nailing 1/20/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/20/2026 Approved OGANES TARAKHCHYAN
Underground Mechanical 2/6/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/4/2026 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 3/4/2026 Approved OGANES TARAKHCHYAN
Final 3/4/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 3/4/2026 Approved OGANES TARAKHCHYAN
HVAC-Final 3/4/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Final 3/4/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV No Gas OGANES TARAKHCHYAN
Service/Power Release 3/4/2026 Approved OGANES TARAKHCHYAN
Smoke Detectors 3/4/2026 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 3/4/2026 Approved OGANES TARAKHCHYAN