12781 W JUDD ST 91331
Certificate Information: 12781 W JUDD ST 91331
- Application / Permit
- 25010-20000-03101
- Plan Check / Job No.
- B25VN19862
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Proposed new detached 2 story ADU of 852 sq.ft PER LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 9/24/2025
- Issuing Office
- Current Status
- Issued on 9/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | RAHEL BEYENE |
| Corrections Issued | 8/11/2025 | RAHEL BEYENE |
| Quality Review Completed | 8/20/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/27/2025 | RAHEL BEYENE |
| Plan Check Approved | 9/22/2025 | RAHEL BEYENE |
| Issued | 9/24/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/15/2025 | ALEX VELA |
| Clean Up Green Up | Cleared | 8/15/2025 | ALEX VELA |
| Tract Map conditions | Cleared | 8/15/2025 | ALEX VELA |
| ZA Case | Cleared | 8/15/2025 | ALEX VELA |
| ZA Case | Cleared | 8/15/2025 | ALEX VELA |
| ZA Case | Cleared | 8/15/2025 | ALEX VELA |
| ZA Case | Cleared | 8/15/2025 | ALEX VELA |
| Address approval | Cleared | 8/17/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 8/17/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 8/25/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/4/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/30/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/6/2026 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/11/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 2/11/2026 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 2/25/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/25/2026 | Partial Approval | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 4/8/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/13/2026 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 4/13/2026 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 4/20/2026 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/29/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/6/2026 | Approved | MICHEL ABAJAN |
| Insulation | 5/12/2026 | Conditional Approval | MICHEL ABAJAN |
| Drywall Nailing | 6/5/2026 | No Result Entered | MICHEL ABAJAN |