12781 W JUDD ST 91331

Certificate Information: 12781 W JUDD ST 91331

Application / Permit
25010-20000-03101
Plan Check / Job No.
B25VN19862
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Proposed new detached 2 story ADU of 852 sq.ft PER LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 9/24/2025
Issuing Office
Current Status
Issued on 9/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 RAHEL BEYENE
Corrections Issued 8/11/2025 RAHEL BEYENE
Quality Review Completed 8/20/2025 HERNAN ARREOLA
Applicant returned to address corrections 8/27/2025 RAHEL BEYENE
Plan Check Approved 9/22/2025 RAHEL BEYENE
Issued 9/24/2025 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 8/15/2025 ALEX VELA
Clean Up Green Up Cleared 8/15/2025 ALEX VELA
Tract Map conditions Cleared 8/15/2025 ALEX VELA
ZA Case Cleared 8/15/2025 ALEX VELA
ZA Case Cleared 8/15/2025 ALEX VELA
ZA Case Cleared 8/15/2025 ALEX VELA
ZA Case Cleared 8/15/2025 ALEX VELA
Address approval Cleared 8/17/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 8/17/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 8/25/2025 DERRICK MAGEE
Sewer availability Cleared 8/25/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/4/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 12/17/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 12/30/2025 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/6/2026 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 2/11/2026 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2026 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 2/11/2026 Approved MICHEL ABAJAN
Deputy Wood Construction 2/25/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 2/25/2026 Partial Approval MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 4/8/2026 Approved MICHEL ABAJAN
HVAC-Rough 4/13/2026 Approved MICHEL ABAJAN
Pre-Inspection 4/13/2026 Approved MICHEL ABAJAN
Pre-Inspection 4/20/2026 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/29/2026 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 5/6/2026 Approved MICHEL ABAJAN
Insulation 5/12/2026 Conditional Approval MICHEL ABAJAN
Drywall Nailing 6/5/2026 No Result Entered MICHEL ABAJAN
Green Building Rough 6/5/2026 No Result Entered MICHEL ABAJAN