20822 W COMMUNITY ST 91306

Certificate Information: 20822 W COMMUNITY ST 91306

Application / Permit
25010-20000-03100
Plan Check / Job No.
B25VN19859
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: New 1-Story Detached ADU per ADU PER GC 66323(a)(2)
Permit Issued
Issued on 12/22/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 KHEDER ALRAZAA
Corrections Issued 8/18/2025 KHEDER ALRAZAA
Quality Review Completed 8/20/2025 GARO TELMI
Applicant returned to address corrections 10/7/2025 KHEDER ALRAZAA
Applicant returned to address corrections 11/7/2025 KHEDER ALRAZAA
Plan Check Approved 11/14/2025 KHEDER ALRAZAA
Issued 12/22/2025 APPLICANT
CofO in Progress 4/27/2026 JEFFREY HARTLINE
Permit Finaled 5/14/2026 JOHN JANSON
CofO Issued 5/14/2026 JOHN JANSON
Permit Finaled 5/14/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/23/2025 LEE GUILBEAUX
Miscellaneous Cleared 8/23/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/23/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/28/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/5/2025 LEE GUILBEAUX
Sewer availability Cleared 9/5/2025 LEE GUILBEAUX
Construction near power lines Cleared 9/15/2025 GEVORK KARAPETYAN
Hold Cleared 1/22/2026 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Kunyoung; Lic. No.: NA66880       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/9/2026 Approved CHRIS CHRISTENSEN
Sewer 1/20/2026 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 1/20/2026 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/26/2026 Corrections Issued CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/29/2026 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 2/19/2026 Partial Approval JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 2/19/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 2/27/2026 Approved JEFFREY HARTLINE
Green Building Rough 2/27/2026 Approved JEFFREY HARTLINE
Insulation 2/27/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/27/2026 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 2/27/2026 Approved JEFFREY HARTLINE
Drywall Nailing 3/4/2026 Corrections Issued JEFFREY HARTLINE
Shower Pan 3/4/2026 Approved JEFFREY HARTLINE
Drywall Nailing 4/21/2026 Approved JEFFREY HARTLINE
Final 4/21/2026 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 4/21/2026 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 4/21/2026 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 4/21/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Final 4/24/2026 Approved JEFFREY HARTLINE
Final 4/24/2026 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 4/24/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 4/24/2026 Approved JEFFREY HARTLINE
Service/Power Release 4/24/2026 Approved JEFFREY HARTLINE