22017 W NAPA ST 91304

Certificate Information: 22017 W NAPA ST 91304

Application / Permit
25010-20000-03093
Plan Check / Job No.
B25VN19821
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'8"X29'0" DETACHED ACCESSORY DWELLING UNIT NEAR SOUTH-EAST CORNER OF LOT. (NFPA13-D FIRE SPRINKLERS REQUIRED THROUGHOUT) [3 OF 3]
Permit Issued
Issued on 2/9/2026
Issuing Office
Valley
Current Status
Issued on 2/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 MARVEL DELACRUZ
Corrections Issued 7/30/2025 MARVEL DELACRUZ
Quality Review Completed 7/31/2025 JASON HEALEY
Building Plans Picked Up 8/1/2025 APPLICANT
Applicant returned to address corrections 9/22/2025 MARVEL DELACRUZ
Applicant returned to address corrections 12/1/2025 MARVEL DELACRUZ
Applicant returned to address corrections 12/9/2025 MARVEL DELACRUZ
Plan Check Approved 12/15/2025 MARVEL DELACRUZ
Issued 2/9/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/7/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/7/2025 LEE GUILBEAUX
Permit Cleared 8/7/2025 LEE GUILBEAUX
Sewer availability Cleared 8/7/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/7/2025 LEE GUILBEAUX
Low Impact Development (LID) Cleared 8/8/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 12/1/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/8/2025 KENNETH FRASER
GPI Written Notices Cleared 12/15/2025 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 12/15/2025 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2026 Partial Approval JEFFREY HARTLINE
Underground Mechanical 3/3/2026 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 3/11/2026 Approved JEFFREY HARTLINE
Deputy Wood Construction 3/24/2026 Conditional Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/27/2026 No Access for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 6/2/2026 Partial Approval JEFFREY HARTLINE