763 N TOYOPA DR 90272
Certificate Information: 763 N TOYOPA DR 90272
- Application / Permit
- 25010-20000-03062
- Plan Check / Job No.
- B25VN19563
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- Issued on 7/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2025 | RARES BODEA |
| Corrections Issued | 7/15/2025 | RARES BODEA |
| Quality Review Completed | 7/15/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/15/2025 | APPLICANT |
| Plan Check Approved | 7/29/2025 | RARES BODEA |
| Issued | 7/31/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | MICHAEL BROWN |
| Permit | Cleared | 7/15/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/15/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/15/2025 | MICHAEL BROWN |
| Low Impact Development (LID) | Cleared | 7/18/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 7/23/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Blue Label Construction Inc; Lic. No.: 972011-B | 2632 WILSHIRE BLVD #363 SANTA MONICA, CA 90403 |
| Engineer | Tani,, Jason; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/20/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/22/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Steel/Welding | 8/25/2025 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 8/26/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/27/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/4/2025 | Approved | TEMISTOCLES CAAL |
| Deputy Wood Construction | 10/21/2025 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 1/6/2026 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 1/7/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/7/2026 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/12/2026 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/12/2026 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/13/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/13/2026 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 1/13/2026 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/20/2026 | Approved | ARAM AVEDISIAN |
| Insulation | 1/20/2026 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/26/2026 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 2/25/2026 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 2/25/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/10/2026 | Approved | STEPHANIE SWANSON |
| Gas Test | 4/23/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/23/2026 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 5/29/2026 | Approved | STEPHANIE SWANSON |