6444-6446 N TYRONE AVE 91401

Certificate Information: 6444-6446 N TYRONE AVE 91401

Application / Permit
25010-20000-03022
Plan Check / Job No.
B25VN19255
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED TWO-STORY SINGLE FAMILY DWELLING PER SB9 TWO UNIT DEVELOPMENT CA GOVT CODE 65852.21 WITH AN ATTACHED TWO-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e) *NFPA-13D FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 2/25/2026
Issuing Office
Current Status
Issued on 2/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2025 APPLICANT
Assigned to Plan Check Engineer 7/10/2025 DANIEL ABRAMYAN
Corrections Issued 7/14/2025 DANIEL ABRAMYAN
Quality Review Completed 7/17/2025 OMID HEDAYAT
Building Plans Picked Up 7/18/2025 APPLICANT
Applicant returned to address corrections 12/17/2025 DANIEL ABRAMYAN
Applicant returned to address corrections 1/28/2026 DANIEL ABRAMYAN
Plan Check Approved 2/25/2026 DANIEL ABRAMYAN
Issued 2/25/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/28/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/29/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/29/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/5/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 8/6/2025 GEVORK KARAPETYAN
Hydrant and Access approval Cleared 8/14/2025 KURT CORRAL
Senate Bill 9 Cleared 1/21/2026 ALEX VELA
Zoning Plan Check Cleared 1/28/2026 DANIEL ABRAMYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mosesian,, Peter; Lic. No.: C95745 86 SMOKE TREE AVE      OAK PARK, CA 91377

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/25/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/25/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 3/31/2026 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/31/2026 Approved VINCENT HANLEY
Sewer 3/31/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/1/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Conditional Approval MICHAEL CORTEZ
HVAC-Rough 5/11/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Rough 5/13/2026 Approved VINCENT HANLEY
PLUMBING-Rough 5/13/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/15/2026 Corrections Issued VINCENT HANLEY
Green Building Rough 5/15/2026 Not Ready for Inspection VINCENT HANLEY
Shower Pan 5/15/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/15/2026 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 6/8/2026 Partial Approval VINCENT HANLEY
Green Building Rough 6/8/2026 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 6/8/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/16/2026 Approved VINCENT HANLEY
Green Building Rough 6/16/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/16/2026 Partial Approval VINCENT HANLEY
Insulation 6/18/2026 Approved VINCENT HANLEY
Drywall Nailing 6/22/2026 Approved VINCENT HANLEY
Green Building Rough 6/22/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/22/2026 Approved VINCENT HANLEY