793-793 1/2 E 41ST ST 90011
Certificate Information: 793-793 1/2 E 41ST ST 90011
- Application / Permit
- 25010-20000-03009
- Plan Check / Job No.
- B25VN19197
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW 2-STORY SFD WITH ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)and (e) WITH ATTACHED 1-CAR GARAGE PER ENGINEERING. NFPA--13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 11/18/2025
- Issuing Office
- Current Status
- Issued on 11/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | ALFRED RAMIREZ |
| Assigned to Zoning Architect | 7/10/2025 | DAVID ZHENG |
| Corrections Issued | 7/13/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 7/16/2025 | STEVEN KIM |
| Applicant returned to address corrections | 11/13/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 11/18/2025 | ALFRED RAMIREZ |
| Issued | 11/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2025 | CINDY QI |
| Low Impact Development (LID) | Cleared | 7/22/2025 | ERNEST TSE |
| Sewer availability | Cleared | 7/22/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 7/25/2025 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 8/21/2025 | CINDY QI |
| Frnt yard landscape/Water mgmt | Cleared | 9/2/2025 | ROSALINDA MEZA |
| Construction near power lines | Cleared | 11/1/2025 | RIDWAN HARDY |
| Zoning Plan Check | Cleared | 11/5/2025 | DAVID ZHENG |
Contact Information
| Contractor | Davidi Construction Inc; Lic. No.: 1107121-B | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/21/2026 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 2/17/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2026 | Approved | JOHN QUINTANILLA |