21112 W CHASE ST 91304
Certificate Information: 21112 W CHASE ST 91304
- Application / Permit
- 25010-20000-02934
- Plan Check / Job No.
- B25VN17455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN***(N) ADU (#2) WITH ATTACHED GARAGE per GCS 66323(a)(4)
- Permit Issued
- Issued on 11/20/2025
- Issuing Office
- Current Status
- Issued on 11/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | SINA KHOSRAVI |
| Assigned to Zoning Architect | 6/26/2025 | JASON BRAVO |
| Corrections Issued | 6/30/2025 | SINA KHOSRAVI |
| Quality Review Completed | 7/9/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/24/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/10/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/14/2025 | SINA KHOSRAVI |
| Plan Check Approved | 11/17/2025 | HERNAN ARREOLA |
| Issued | 11/20/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/22/2025 | LAVEON RIDER |
| Address approval | Cleared | 8/20/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 9/17/2025 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 10/25/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/27/2025 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 11/6/2025 | SINA KHOSRAVI |
Contact Information
| Contractor | Aoa Capital Builders Inc; Lic. No.: 1136599-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 12/22/2025 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 1/5/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 1/5/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 1/5/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2026 | No Access for Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 2/19/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 2/19/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/19/2026 | Approved | JEFFREY HARTLINE |
| Shower Pan | 2/23/2026 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/26/2026 | Partial Approval | JEFFREY HARTLINE |
| Deputy Wood Construction | 3/3/2026 | Conditional Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 3/9/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/9/2026 | Partial Approval | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 3/9/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 3/11/2026 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 3/20/2026 | Approved | JEFFREY HARTLINE |