19106 W HALSTED ST 91324
Certificate Information: 19106 W HALSTED ST 91324
- Application / Permit
- 25010-20000-02909
- Plan Check / Job No.
- B25VN18594
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan - (n) detached 1-story ADU w/ wood deck per GC 66323(a)(2) R3 occupancy
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Current Status
- Issued on 12/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | KELVIN CHUONG |
| Corrections Issued | 7/4/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/21/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/31/2025 | SUNMIN LEE |
| Plan Check Approved | 8/4/2025 | KELVIN CHUONG |
| Issued | 12/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2025 | ROSE MARIE SMITH |
Contact Information
| Contractor | Buildoly Inc; Lic. No.: 1134744-B | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/22/2025 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 12/22/2025 | Partial Approval | DAVID SCANTLIN |
| Sewer | 12/23/2025 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 1/26/2026 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Approved | DAVID SCANTLIN |
| Wood Frame | 2/24/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/23/2026 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 3/23/2026 | Approved | JACK KARGODORIAN |
| Sewer | 3/23/2026 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/25/2026 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/25/2026 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/9/2026 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/13/2026 | Approved | JACK KARGODORIAN |
| Green Building Rough | 4/13/2026 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 4/13/2026 | Corrections Issued | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 4/13/2026 | Approved | JACK KARGODORIAN |
| Insulation | 4/24/2026 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 5/4/2026 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 5/11/2026 | Approved | JEFFREY PARD |