11333 W MIRANDA ST 91601
Certificate Information: 11333 W MIRANDA ST 91601
- Application / Permit
- 25010-20000-02870
- Plan Check / Job No.
- B25VN18365
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). WORK PER ENGINEERED DESIGN. **SEE COMMENTS
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- Issued on 8/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 7/2/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 8/25/2025 | OMAR GARNICA |
| Issued | 8/27/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 8/7/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 8/11/2025 | MICHAEL BROWN |
Contact Information
| Architect | Saivar,, Timothy Martin; Lic. No.: C13727 | 15594 MALLORY CT MOORPARK, CA 93021 |
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/29/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 10/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 11/13/2025 | Corrections Issued | JOSE AVILA |
| Wood Frame | 11/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 12/16/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/3/2026 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/3/2026 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/11/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| Insulation | 3/18/2026 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 3/18/2026 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 3/31/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/31/2026 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 4/15/2026 | Approved | GAREN HAYRAPETYAN |