4182-4182 1/2 N TUJUNGA AVE 91604

Certificate Information: 4182-4182 1/2 N TUJUNGA AVE 91604

Application / Permit
25010-20000-02859
Plan Check / Job No.
B25VN18307
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY (40' X 31'-10") DUPLEX. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 3/17/2026
Issuing Office
Valley
Current Status
Issued on 3/17/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/26/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 VAHAN JIVALAGIAN
Corrections Issued 6/29/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 7/3/2025 KAREN MEZA-MORALES
Quality Review Completed 7/8/2025 OMID HEDAYAT
Building Plans Picked Up 7/10/2025 APPLICANT
Plan Check Approved 3/13/2026 VAHAN JIVALAGIAN
Issued 3/17/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/23/2025 STEVE MELGAR
Miscellaneous Cleared 7/25/2025 RYAN CASTRO
Construction near power lines Cleared 7/26/2025 ENRIQUE ACOSTA
Hydrant and Access approval Cleared 7/29/2025 PATRICK PEREZ
Roof/Waste drainage to street Cleared 8/6/2025 RYAN CASTRO
Trees in Parkway Cleared 9/5/2025 RICHARD SANCHEZ
Frnt yard landscape/Water mgmt Cleared 9/15/2025 ROSALINDA MEZA
ZI Cleared 9/15/2025 ROSALINDA MEZA
Sewer availability Cleared 11/20/2025 COLIN LOREDO
Highway dedication Cleared 11/24/2025 COLIN LOREDO
Permit Cleared 11/24/2025 COLIN LOREDO
"Q" conditions Cleared 12/23/2025 ROSALINDA MEZA
Address approval Cleared 12/24/2025 JEREMY CHOK
Zoning Plan Check Cleared 1/21/2026 KAREN MEZA-MORALES
SB8 RUD Cleared 2/4/2026 ASHLEY MEDINA

Contact Information

Contractor S & K Quality Builders Inc; Lic. No.: 1026841-B 2079 E 15 STREET STE 336      LOS ANGELES, CA 90021
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/28/2026 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 6/12/2026 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 6/15/2026 Partial Approval JAVIER RAMOS JR
Sewer 6/22/2026 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 6/26/2026 Approved JAVIER RAMOS JR
Deputy Wood Construction 7/17/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/20/2026 Partial Approval JAVIER RAMOS JR