406 N BEIRUT AVE 90272
Certificate Information: 406 N BEIRUT AVE 90272
- Application / Permit
- 25010-20000-02850
- Plan Check / Job No.
- B25LA25332
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Eplan **2025 Wildfire ELIGIBLE Project** Rebuild a new detached two car garage, all work per engineering
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | RARES BODEA |
| Corrections Issued | 6/26/2025 | RARES BODEA |
| Quality Review Completed | 6/27/2025 | STEVEN KIM |
| Applicant returned to address corrections | 7/8/2025 | RARES BODEA |
| Applicant returned to address corrections | 7/22/2025 | RARES BODEA |
| Applicant returned to address corrections | 7/24/2025 | RARES BODEA |
| Applicant returned to address corrections | 8/11/2025 | RARES BODEA |
| Plan Check Approved | 8/13/2025 | RARES BODEA |
| No Progress | 8/13/2025 | RARES BODEA |
| Plan Check Approved | 8/13/2025 | RARES BODEA |
| Issued | 8/13/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | JUAN VALENZUELA |
| Permit Finaled | 5/13/2026 | RICHARD STEINBACH |
| CofO Issued | 5/13/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/13/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | DAVID LOPEZ |
| Construction within easement | Cleared | 7/21/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2025 | Conditional Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/11/2025 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/11/2025 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 12/11/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/29/2025 | Approved | KENNETH NAGLE |
| Green Building Rough | 12/29/2025 | Approved | KENNETH NAGLE |
| Insulation | 12/29/2025 | Approved | KENNETH NAGLE |
| Drywall Nailing | 2/13/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/9/2026 | Approved | STEPHANIE SWANSON |
| Final | 4/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/9/2026 | Approved | STEPHANIE SWANSON |
| Green Building Final | 4/9/2026 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/15/2026 | Approved | STEPHANIE SWANSON |
| Final | 4/15/2026 | OK to Issue CofO | STEPHANIE SWANSON |
| Service/Power Release | 4/15/2026 | Approved | STEPHANIE SWANSON |