Certificate Information: 406 N BEIRUT AVE 90272

Application / Permit
25010-20000-02850
Plan Check / Job No.
B25LA25332
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Eplan **2025 Wildfire ELIGIBLE Project** Rebuild a new detached two car garage, all work per engineering
Permit Issued
Issued on 8/13/2025
Issuing Office
Current Status
CofO Issued on 5/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2025 APPLICANT
Assigned to Plan Check Engineer 6/24/2025 RARES BODEA
Corrections Issued 6/26/2025 RARES BODEA
Quality Review Completed 6/27/2025 STEVEN KIM
Applicant returned to address corrections 7/8/2025 RARES BODEA
Applicant returned to address corrections 7/22/2025 RARES BODEA
Applicant returned to address corrections 7/24/2025 RARES BODEA
Applicant returned to address corrections 8/11/2025 RARES BODEA
Plan Check Approved 8/13/2025 RARES BODEA
No Progress 8/13/2025 RARES BODEA
Plan Check Approved 8/13/2025 RARES BODEA
Issued 8/13/2025 APPLICANT
CofO in Progress 5/13/2026 JUAN VALENZUELA
Permit Finaled 5/13/2026 RICHARD STEINBACH
CofO Issued 5/13/2026 RICHARD STEINBACH
Permit Finaled 5/13/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 7/11/2025 DAVID LOPEZ
Construction within easement Cleared 7/21/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/10/2025 Conditional Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 12/11/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 12/11/2025 Partial Approval STEPHANIE SWANSON
Shower Pan 12/11/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 12/29/2025 Approved KENNETH NAGLE
Green Building Rough 12/29/2025 Approved KENNETH NAGLE
Insulation 12/29/2025 Approved KENNETH NAGLE
Drywall Nailing 2/13/2026 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/9/2026 Approved STEPHANIE SWANSON
Final 4/9/2026 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 4/9/2026 Approved STEPHANIE SWANSON
Green Building Final 4/9/2026 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/15/2026 Approved STEPHANIE SWANSON
Final 4/15/2026 OK to Issue CofO STEPHANIE SWANSON
Service/Power Release 4/15/2026 Approved STEPHANIE SWANSON