8450 N LOUISE AVE 91325

Certificate Information: 8450 N LOUISE AVE 91325

Application / Permit
25010-20000-02831
Plan Check / Job No.
B25VN18100
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 1-Story Single family dwelling per SB 9 (Rear BLDG) Fire Sprinkler throughout
Permit Issued
Issued on 9/25/2025
Issuing Office
Current Status
Issued on 9/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2025 APPLICANT
Assigned to Plan Check Engineer 7/17/2025 KHEDER ALRAZAA
Corrections Issued 7/28/2025 KHEDER ALRAZAA
Quality Review Completed 7/29/2025 GARO TELMI
Applicant returned to address corrections 9/3/2025 KHEDER ALRAZAA
Plan Check Approved 9/24/2025 KHEDER ALRAZAA
Issued 9/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/2/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 8/5/2025 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 8/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 8/7/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 8/13/2025 KURT CORRAL
Low Impact Development (LID) Cleared 8/22/2025 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/26/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/1/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 10/1/2025 Partial Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 10/8/2025 Approved NICHOLAS TROWBRIDGE
Deputy Reinf. Concrete 10/9/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 12/1/2025 Approved WILLIAM WREN
PLUMBING-Rough 12/1/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 12/8/2025 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 12/8/2025 Not Ready for Inspection KEVIN BERBERYAN
Verify Sprinkler Sign Off 12/8/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 12/10/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 12/15/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 12/17/2025 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 12/17/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/15/2026 Approved CHRISTOPHER ROJAS
Insulation 1/15/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/15/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 1/27/2026 Approved CHRISTOPHER ROJAS
Shower Pan 2/19/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/4/2026 Approved CHRISTOPHER ROJAS
Shower Pan 3/4/2026 Approved CHRISTOPHER ROJAS