8450 N LOUISE AVE 91325
Certificate Information: 8450 N LOUISE AVE 91325
- Application / Permit
- 25010-20000-02831
- Plan Check / Job No.
- B25VN18100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. New 1-Story Single family dwelling per SB 9 (Rear BLDG) Fire Sprinkler throughout
- Permit Issued
- Issued on 9/25/2025
- Issuing Office
- Current Status
- Issued on 9/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | KHEDER ALRAZAA |
| Corrections Issued | 7/28/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 7/29/2025 | GARO TELMI |
| Applicant returned to address corrections | 9/3/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 9/24/2025 | KHEDER ALRAZAA |
| Issued | 9/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2025 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 8/5/2025 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/7/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 8/13/2025 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 8/22/2025 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/26/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 10/1/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Reinf. Concrete | 10/9/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 12/1/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 12/1/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/8/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/8/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 12/8/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/10/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 12/15/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/17/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Special/Order Compliance | 12/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 1/15/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/15/2026 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/27/2026 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 2/19/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/4/2026 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 3/4/2026 | Approved | CHRISTOPHER ROJAS |