1550 W 222ND ST 90501

Certificate Information: 1550 W 222ND ST 90501

Application / Permit
25010-20000-02820
Plan Check / Job No.
B25VN18063
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 26' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/25/2025
Issuing Office
Current Status
CofO Issued on 5/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 SELLA BENYAMIN
Corrections Issued 7/1/2025 SELLA BENYAMIN
Quality Review Completed 7/1/2025 STEVEN KIM
Building Plans Picked Up 7/2/2025 APPLICANT
Plan Check Approved 8/22/2025 SELLA BENYAMIN
Issued 8/25/2025 APPLICANT
CofO in Progress 3/27/2026 ARTHUR NEGRETE
Permit Finaled 5/20/2026 ANSON MAGLASANG
CofO Issued 5/20/2026 ANSON MAGLASANG
Permit Finaled 5/20/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/7/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 7/7/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/22/2025 JEANIE LAM
Sewer availability Cleared 8/22/2025 JEANIE LAM

Contact Information

Contractor K N Remodeling And Supplies Inc; Lic. No.: 978086-B 19709 VENTURA BLVD STE 202      WOODLAND HILLS, CA 91364
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/29/2025 Partial Approval JOSEPH MCGARRY
Underground Mechanical 8/29/2025 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/5/2025 Approved EUGENE CASSIDY
Footing/Foundation/Slab 9/5/2025 Approved EUGENE CASSIDY
METHANE-Barrier 9/5/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 9/5/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/16/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 9/16/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 9/16/2025 Approved EUGENE CASSIDY
Underground Mechanical 9/16/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 9/16/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/26/2025 Corrections Issued EUGENE CASSIDY
Deputy Wood Construction 9/26/2025 Approved EUGENE CASSIDY
Green Building Rough 9/26/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/9/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 10/9/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 10/9/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 10/9/2025 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/9/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/22/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/22/2025 Approved EUGENE CASSIDY
Green Building Rough 10/22/2025 Approved EUGENE CASSIDY
HVAC-Rough 10/22/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 10/22/2025 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/22/2025 Approved EUGENE CASSIDY
Insulation 10/27/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 10/27/2025 Partial Approval BEN MOLSTAD
Drywall Nailing 10/31/2025 Approved EUGENE CASSIDY
Final 12/11/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 12/11/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 12/11/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/11/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/26/2026 Approved ARTHUR NEGRETE
Final 3/26/2026 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 3/26/2026 Approved ARTHUR NEGRETE
HVAC-Final 3/26/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/26/2026 Approved ARTHUR NEGRETE
Service/Power Release 3/26/2026 Approved ARTHUR NEGRETE