1550 W 222ND ST 90501
Certificate Information: 1550 W 222ND ST 90501
- Application / Permit
- 25010-20000-02820
- Plan Check / Job No.
- B25VN18063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22' X 26' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 8/25/2025
- Issuing Office
- Current Status
- CofO Issued on 5/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | SELLA BENYAMIN |
| Corrections Issued | 7/1/2025 | SELLA BENYAMIN |
| Quality Review Completed | 7/1/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/2/2025 | APPLICANT |
| Plan Check Approved | 8/22/2025 | SELLA BENYAMIN |
| Issued | 8/25/2025 | APPLICANT |
| CofO in Progress | 3/27/2026 | ARTHUR NEGRETE |
| Permit Finaled | 5/20/2026 | ANSON MAGLASANG |
| CofO Issued | 5/20/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/20/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/7/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2025 | JEANIE LAM |
| Sewer availability | Cleared | 8/22/2025 | JEANIE LAM |
Contact Information
| Contractor | K N Remodeling And Supplies Inc; Lic. No.: 978086-B | 19709 VENTURA BLVD STE 202 WOODLAND HILLS, CA 91364 |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/29/2025 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 8/29/2025 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 9/5/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/5/2025 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 9/5/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 9/5/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/16/2025 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 9/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 9/16/2025 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 9/16/2025 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 9/16/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/26/2025 | Corrections Issued | EUGENE CASSIDY |
| Deputy Wood Construction | 9/26/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/26/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/9/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/9/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/9/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 10/9/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 10/9/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/22/2025 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/22/2025 | Approved | EUGENE CASSIDY |
| Insulation | 10/27/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | BEN MOLSTAD |
| Drywall Nailing | 10/31/2025 | Approved | EUGENE CASSIDY |
| Final | 12/11/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/11/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 12/11/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/26/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/26/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 3/26/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 3/26/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/26/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/26/2026 | Approved | ARTHUR NEGRETE |