NEW DETACHED 25'-4" X 32'-10" SINGLE FAMILY DWELLING PER SB9 WITH ATTACHED 25'-4" X 8'-0" TRELLIS AND 4'-11" X 7'-10" COVERED ENTRY *NFPA-13D FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 12/11/2025
Issuing Office
Current Status
Issued on 12/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/20/2025 APPLICANT
Assigned to Zoning Architect 6/26/2025 RYAN DEL POSO
Assigned to Plan Check Engineer 7/2/2025 DANIEL ABRAMYAN
Corrections Issued 7/16/2025 DANIEL ABRAMYAN
Quality Review Completed 7/24/2025 OMID HEDAYAT
Building Plans Picked Up 10/8/2025 APPLICANT
Applicant returned to address corrections 11/21/2025 DANIEL ABRAMYAN
Plan Check Approved 12/11/2025 DANIEL ABRAMYAN
Issued 12/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/21/2025 CINDY QI
Address approval Cleared 7/21/2025 CINDY QI
BHO/Hillside ordinance Cleared 7/21/2025 CINDY QI
BHO/Hillside ordinance Cleared 7/21/2025 CINDY QI
BHO/Hillside ordinance Cleared 7/21/2025 CINDY QI
BHO/Hillside ordinance Cleared 7/21/2025 CINDY QI
BHO/Hillside ordinance Cleared 7/21/2025 CINDY QI
Roof/Waste drainage to street Cleared 7/21/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/22/2025 CINDY QI
Sewer availability Cleared 7/22/2025 CINDY QI
Senate Bill 9 Cleared 10/23/2025 JACQUELINE TORRES
Frnt yard landscape/Water mgmt Cleared 11/3/2025 JACQUELINE TORRES
ZA Case Cleared 11/3/2025 JACQUELINE TORRES
ZI Cleared 11/3/2025 JACQUELINE TORRES
Hydrant and Access approval Cleared 11/4/2025 KURT CORRAL
Grading Pre-Inspection Cleared 11/4/2025 RUSSELL BONVOULOIR
Zoning Plan Check Cleared 11/17/2025 RYAN DEL POSO
GPI Written Notices Cleared 12/11/2025 DANIEL ABRAMYAN

Contact Information

Contractor We The People Construction Inc; Lic. No.: 1076924-B 5352 LAUREL CANYON BLVD # 200      VALLEY VILLAGE, CA 91607

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/23/2026 Not Ready for Inspection RONNIE MEDINA
Underground Mechanical 1/26/2026 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 1/30/2026 Approved DAVID WILLIAMS
Footing/Foundation/Slab 1/30/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Partial Approval DAVID WILLIAMS
BUILDING-Rough-Frame 3/25/2026 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 3/25/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 3/25/2026 Approved DAVID WILLIAMS
Green Building Rough 3/25/2026 Approved DAVID WILLIAMS
HVAC-Rough 3/25/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 3/25/2026 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 3/25/2026 Not Ready for Inspection DAVID WILLIAMS
Insulation 4/6/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 4/6/2026 Partial Approval DAVID WILLIAMS
Drywall Nailing 4/14/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 5/4/2026 Approved DAVID WILLIAMS
Shower Pan 5/4/2026 Approved DAVID WILLIAMS