5681 E STRATFORD ROAD 90042
Certificate Information: 5681 E STRATFORD ROAD 90042
- Application / Permit
- 25010-20000-02767
- Plan Check / Job No.
- B25VN17717
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW DETACHED 25'-4" X 32'-10" SINGLE FAMILY DWELLING PER SB9 WITH ATTACHED 25'-4" X 8'-0" TRELLIS AND 4'-11" X 7'-10" COVERED ENTRY *NFPA-13D FIRE SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 12/11/2025
- Issuing Office
- Current Status
- Issued on 12/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Zoning Architect | 6/26/2025 | RYAN DEL POSO |
| Assigned to Plan Check Engineer | 7/2/2025 | DANIEL ABRAMYAN |
| Corrections Issued | 7/16/2025 | DANIEL ABRAMYAN |
| Quality Review Completed | 7/24/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 10/8/2025 | APPLICANT |
| Applicant returned to address corrections | 11/21/2025 | DANIEL ABRAMYAN |
| Plan Check Approved | 12/11/2025 | DANIEL ABRAMYAN |
| Issued | 12/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2025 | CINDY QI |
| Address approval | Cleared | 7/21/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/21/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/21/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/21/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/21/2025 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/21/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 7/21/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2025 | CINDY QI |
| Sewer availability | Cleared | 7/22/2025 | CINDY QI |
| Senate Bill 9 | Cleared | 10/23/2025 | JACQUELINE TORRES |
| Frnt yard landscape/Water mgmt | Cleared | 11/3/2025 | JACQUELINE TORRES |
| ZA Case | Cleared | 11/3/2025 | JACQUELINE TORRES |
| ZI | Cleared | 11/3/2025 | JACQUELINE TORRES |
| Hydrant and Access approval | Cleared | 11/4/2025 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 11/4/2025 | RUSSELL BONVOULOIR |
| Zoning Plan Check | Cleared | 11/17/2025 | RYAN DEL POSO |
| GPI Written Notices | Cleared | 12/11/2025 | DANIEL ABRAMYAN |
Contact Information
| Contractor | We The People Construction Inc; Lic. No.: 1076924-B | 5352 LAUREL CANYON BLVD # 200 VALLEY VILLAGE, CA 91607 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/23/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Underground Mechanical | 1/26/2026 | Partial Approval | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 1/30/2026 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 1/30/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Partial Approval | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 3/25/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 3/25/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Approved | DAVID WILLIAMS |
| Green Building Rough | 3/25/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 3/25/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 3/25/2026 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 3/25/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Insulation | 4/6/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/6/2026 | Partial Approval | DAVID WILLIAMS |
| Drywall Nailing | 4/14/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/4/2026 | Approved | DAVID WILLIAMS |
| Shower Pan | 5/4/2026 | Approved | DAVID WILLIAMS |