764-764 1/2 E 52ND ST 90011

Certificate Information: 764-764 1/2 E 52ND ST 90011

Application / Permit
25010-20000-02743
Plan Check / Job No.
B25VN17516
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 2/2/2026
Issuing Office
Current Status
Issued on 2/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/19/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 HERNAN ARREOLA
Corrections Issued 6/30/2025 HERNAN ARREOLA
Quality Review Completed 7/9/2025 GARO TELMI
Plan Check Approved 1/5/2026 HERNAN ARREOLA
Issued 2/2/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/26/2025 JEREMY CHOK
Hydrant and Access approval Cleared 7/28/2025 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 7/29/2025 JEREMY CHOK
Permit Cleared 11/17/2025 JEREMY CHOK
Sewer availability Cleared 11/17/2025 JEREMY CHOK
Low Impact Development (LID) Cleared 12/4/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 12/5/2025 JEREMY CHOK
SB8 RUD Cleared 12/9/2025 DORIS KWOK

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/24/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/24/2026 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 2/25/2026 Conditional Approval GEM DE OCAMPO
Sewer 3/6/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/6/2026 Approved ALEJANDRO DE ARTOLA
Wood Frame 3/6/2026 Partial Approval ALEJANDRO DE ARTOLA
Insulation 3/9/2026 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/10/2026 Approved MICHAEL LEWIS
PLUMBING-Rough 4/23/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/15/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 5/15/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/19/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 5/20/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 5/20/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/26/2026 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 5/26/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/26/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/27/2026 Approved ALEJANDRO DE ARTOLA
Insulation 5/27/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/27/2026 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 6/3/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/3/2026 Partial Approval ALEJANDRO DE ARTOLA