4541 N VAN NOORD AVE 91604

Certificate Information: 4541 N VAN NOORD AVE 91604

Application / Permit
25010-20000-02737
Plan Check / Job No.
B25VN17478
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42' X 17'-4" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 8/14/2025
Issuing Office
Current Status
Issued on 8/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 SELLA BENYAMIN
Corrections Issued 7/1/2025 SELLA BENYAMIN
Building Plans Picked Up 7/14/2025 APPLICANT
Quality Review Completed 8/14/2025 SELLA BENYAMIN
Plan Check Approved 8/14/2025 SELLA BENYAMIN
Issued 8/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/10/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/11/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/11/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 7/18/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Amar,, David; Lic. No.: C97582 6160 CORBIN AVENUE      TARZANA, CA 91356

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/15/2025 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 10/30/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/30/2025 Approved CHRISTOPHE COCHRAN
Deputy Steel/Welding 11/5/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/13/2026 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/13/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/20/2026 Corrections Issued MICHAEL CORTEZ
HVAC-Rough 4/13/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/13/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/29/2026 Approved CHRISTOPHE COCHRAN
Underground Mechanical 4/29/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/14/2026 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/20/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/20/2026 Partial Inspection GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 5/20/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/20/2026 Off-Hour Fees Due
Green Building Rough 5/20/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/20/2026 Partial Inspection GAREN HAYRAPETYAN
Special/Order Compliance 5/20/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 5/20/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 5/20/2026 Partial Inspection GAREN HAYRAPETYAN
Insulation 5/29/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/29/2026 Approved CHRISTOPHE COCHRAN
Shower Pan 5/29/2026 Approved CHRISTOPHE COCHRAN
Insulation 6/3/2026 Approved CHRISTOPHE COCHRAN
Shower Pan 6/3/2026 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/11/2026 Approved RAUL OLAGI