21114 W CHASE ST 1-3 91304

Certificate Information: 21114 W CHASE ST 1-3 91304

Application / Permit
25010-20000-02735
Plan Check / Job No.
B25VN17455
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN*** DUPLEX PER SB9 WITH ATTACHED GARAGE AND ADU
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 SINA KHOSRAVI
Assigned to Zoning Architect 6/26/2025 JASON BRAVO
Corrections Issued 6/30/2025 SINA KHOSRAVI
Quality Review Completed 7/9/2025 HERNAN ARREOLA
Applicant returned to address corrections 10/24/2025 SINA KHOSRAVI
Applicant returned to address corrections 11/10/2025 SINA KHOSRAVI
Applicant returned to address corrections 11/14/2025 SINA KHOSRAVI
Plan Check Approved 11/17/2025 HERNAN ARREOLA
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/22/2025 LAVEON RIDER
Address approval Cleared 8/20/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/20/2025 RYAN CASTRO
Sewer availability Cleared 9/17/2025 CARLOS AGUILERA
Trees in Parkway Cleared 9/19/2025 RICHARD SANCHEZ
Low Impact Development (LID) Cleared 10/25/2025 MITESH PATEL
Permit Cleared 10/27/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/27/2025 LEE GUILBEAUX
Zoning Plan Check Cleared 10/31/2025 Gurunath Nesarajah

Contact Information

Contractor Aoa Capital Builders Inc; Lic. No.: 1136599-B       ,
Engineer Le,, Thang Huu; Lic. No.: NA4978       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/5/2026 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 1/7/2026 Partial Approval TROY SANDERS
Footing/Foundation/Slab 1/12/2026 Partial Approval JEFFREY HARTLINE
Underground Mechanical 1/12/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/16/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 1/16/2026 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 1/16/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 No Access for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Corrections Issued JEFFREY HARTLINE
HVAC-Rough 2/11/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 2/19/2026 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 2/19/2026 Approved JEFFREY HARTLINE
PLUMBING-Rough 2/19/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 2/23/2026 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 2/23/2026 Not Ready for Inspection JEFFREY HARTLINE
Shower Pan 2/23/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 2/26/2026 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 2/26/2026 Partial Approval JEFFREY HARTLINE
Deputy Wood Construction 3/3/2026 Conditional Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 3/9/2026 Not Ready for Inspection JEFFREY HARTLINE
Green Building Rough 3/9/2026 Approved JEFFREY HARTLINE
Insulation 3/9/2026 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 3/9/2026 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 3/9/2026 Not Ready for Inspection JEFFREY HARTLINE
Wood Frame 3/9/2026 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 3/11/2026 Approved JEFFREY HARTLINE
Green Building Rough 3/11/2026 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 3/11/2026 Approved JEFFREY HARTLINE
Insulation 3/12/2026 Not Ready for Inspection JEFFREY HARTLINE
Wood Frame 3/12/2026 Approved JEFFREY HARTLINE
Insulation 3/16/2026 Approved CHRIS CHRISTENSEN
Drywall Nailing 3/23/2026 Approved DAVID SCANTLIN
Sewer 4/22/2026 Approved JEFFREY HARTLINE