7814 N AMESTOY AVE 91406

Certificate Information: 7814 N AMESTOY AVE 91406

Application / Permit
25010-20000-02646
Plan Check / Job No.
B25VN16969
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). ALL WORK PER WFPP.
Permit Issued
Issued on 8/28/2025
Issuing Office
Current Status
CofO Issued on 6/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/23/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/23/2025 APPLICANT
Issued 8/28/2025 APPLICANT
CofO in Progress 5/7/2026 KIRK SANDERS
CofO Issued 6/30/2026 RUBEN SALAS
Permit Finaled 6/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/28/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 7/28/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/28/2025 MICHAEL BROWN
Sewer availability Cleared 7/28/2025 MICHAEL BROWN
Hydrant and Access approval Cleared 8/5/2025 FRANK GOMEZ
Construction within easement Cleared 8/20/2025 RIDWAN HARDY
Construction near power lines Cleared 8/21/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/11/2025 Partial Approval GAREN HAYRAPETYAN
Underground Mechanical 9/11/2025 Partial Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 9/16/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 10/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 10/6/2025 No Access for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 11/6/2025 Corrections Issued GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 11/6/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/24/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/24/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/24/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 11/24/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/24/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 11/24/2025 Approved GAREN HAYRAPETYAN
Insulation 12/3/2025 Approved JUAN VALENZUELA
Drywall Nailing 12/16/2025 Approved CHRISTOPHER MORFIN
Sewer 12/23/2025 Approved MICHAEL CORTEZ
Shower Pan 12/23/2025 Approved MICHAEL CORTEZ
Deputy Wood Construction 12/26/2025 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 12/26/2025 Not Ready for Inspection JACK KARGODORIAN
Underground Mechanical 12/30/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/12/2026 Approved GAREN HAYRAPETYAN
Shower Pan 1/12/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 4/15/2026 Corrections Issued KIRK SANDERS
Final 4/15/2026 Not Ready for Inspection KIRK SANDERS
Gas Test 4/15/2026 Approved KIRK SANDERS
Green Building Final 4/15/2026 Not Ready for Inspection KIRK SANDERS
HVAC-Final 4/15/2026 Corrections Issued KIRK SANDERS
PLUMBING-Final 4/15/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Required KIRK SANDERS
Service/Power Release 4/15/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 4/15/2026 Approved KIRK SANDERS
ELECTRICAL-Final 4/21/2026 Not Ready for Inspection JOSE AVILA
Final 4/21/2026 Not Ready for Inspection JOSE AVILA
Green Building Final 4/21/2026 Not Ready for Inspection JOSE AVILA
HVAC-Final 4/21/2026 Approved JOSE AVILA
ELECTRICAL-Final 5/6/2026 Approved KIRK SANDERS
Final 5/6/2026 OK to Issue CofO KIRK SANDERS
Green Building Final 5/6/2026 Approved KIRK SANDERS
Service/Power Release 5/6/2026 Approved KIRK SANDERS