5822 N DENNY AVE 91601

Certificate Information: 5822 N DENNY AVE 91601

Application / Permit
25010-20000-02627
Plan Check / Job No.
B25VN16700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(b)(1),(c),(d),(h), AND (k). WORK DONE PER WFPP DESIGN. ORDER TO COMPLY ISSUED: 11/17/2016
Permit Issued
Issued on 8/7/2025
Issuing Office
Current Status
CofO in Progress on 5/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2025 APPLICANT
Assigned to Plan Check Engineer 6/17/2025 MADISON ODELL
Corrections Issued 6/17/2025 MADISON ODELL
Applicant returned to address corrections 7/22/2025 MADISON ODELL
Plan Check Approved 8/6/2025 ALEC MOUSAKHANIAN
Issued 8/7/2025 APPLICANT
CofO in Progress 5/7/2026 ROBERTO PALACIOS-LOPEZ

Permit Application Clearance Information

Address approval Cleared 7/11/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/11/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/14/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/14/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/15/2025 Corrections Issued MARK VAN SLOOTEN
Excavation/Setback/Form/Re-Bar 10/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 11/17/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 12/10/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/17/2025 Approved JOSE AVILA
ELECTRICAL-Rough 12/29/2025 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 12/29/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 12/29/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/8/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/8/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ
Insulation 1/8/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 1/8/2026 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 4/28/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/28/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/28/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 5/1/2026 Corrections Issued MICHAEL CORTEZ
Final 5/5/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/5/2026 Approved ROBERTO PALACIOS-LOPEZ