10210 N WYSTONE AVE 91324

Certificate Information: 10210 N WYSTONE AVE 91324

Application / Permit
25010-20000-02614
Plan Check / Job No.
B25VN16612
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per GC 66323(a)(2).
Permit Issued
Issued on 7/11/2025
Issuing Office
Current Status
CofO Issued on 3/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2025 APPLICANT
Assigned to Plan Check Engineer 6/16/2025 CAROLEAN BASMA
Corrections Issued 6/17/2025 CAROLEAN BASMA
Plan Check Approved 6/30/2025 CAROLEAN BASMA
Issued 7/11/2025 APPLICANT
CofO in Progress 3/2/2026 DAVID SCANTLIN
Permit Finaled 3/4/2026 JOHN JANSON
CofO Issued 3/4/2026 JOHN JANSON
Permit Finaled 3/4/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/18/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/18/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/18/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/20/2025 LEE GUILBEAUX
Sewer availability Cleared 6/20/2025 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor K M Builders; Lic. No.: 1080573-B       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2025 Corrections Issued DAVID SCANTLIN
PLUMBING-Rough 8/11/2025 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 8/18/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 9/5/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/5/2025 Partial Approval DAVID SCANTLIN
Green Building Rough 9/5/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 9/5/2025 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 9/5/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 9/10/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/10/2025 Approved DAVID SCANTLIN
Green Building Rough 9/10/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 9/10/2025 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 9/10/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/12/2025 Approved DAVID SCANTLIN
HVAC-Rough 9/12/2025 Corrections Issued DAVID SCANTLIN
PLUMBING-Rough 9/12/2025 Corrections Issued DAVID SCANTLIN
HVAC-Rough 9/16/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 9/16/2025 Approved DAVID SCANTLIN
HVAC-Rough 9/19/2025 Corrections Issued DAVID SCANTLIN
HVAC-Rough 9/25/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/1/2025 Corrections Issued DAVID SCANTLIN
Green Building Rough 10/1/2025 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 10/1/2025 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 10/10/2025 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 10/27/2025 Conditional Approval ARUTYUN MADATYAN
Green Building Rough 10/27/2025 Approved ARUTYUN MADATYAN
Insulation 10/27/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/31/2025 Approved DAVID SCANTLIN
Drywall Nailing 10/31/2025 Approved DAVID SCANTLIN
Green Building Rough 10/31/2025 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 10/31/2025 Approved DAVID SCANTLIN
Shower Pan 11/3/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 11/5/2025 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 11/5/2025 Approved DAVID SCANTLIN
Underground Mechanical 11/6/2025 Not Ready for Inspection DAVID SCANTLIN
Sewer 11/10/2025 Approved DAVID SCANTLIN
Underground Mechanical 11/18/2025 Approved DAVID SCANTLIN
Underground Mechanical 11/20/2025 Approved KRISTEN CAUSEY
Final 2/26/2026 Corrections Issued DAVID SCANTLIN
Green Building Final 2/26/2026 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved DAVID SCANTLIN
Service/Power Release 2/26/2026 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 2/26/2026 Approved DAVID SCANTLIN
Final 3/2/2026 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 3/2/2026 Approved DAVID SCANTLIN