9400 N ENCINO AVE 91325

Certificate Information: 9400 N ENCINO AVE 91325

Application / Permit
25010-20000-02608
Plan Check / Job No.
B25VN16562
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
New Detached Rec Room 450 sq.ft.
Permit Issued
Issued on 8/22/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2025 APPLICANT
Assigned to Plan Check Engineer 6/13/2025 JOHN MESIAS
Corrections Issued 6/13/2025 JOHN MESIAS
Applicant returned to address corrections 7/31/2025 JOHN MESIAS
Plan Check Approved 8/7/2025 JOHN MESIAS
Issued 8/22/2025 APPLICANT
CofO in Progress 4/15/2026 KEVIN BERBERYAN
Permit Finaled 5/14/2026 RUBEN SALAS
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/20/2025 COLIN LOREDO
Sewer availability Cleared 6/20/2025 COLIN LOREDO
Hydrant and Access approval Cleared 7/16/2025 KURT CORRAL
Construction near power lines Cleared 7/30/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 7/30/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/5/2025 Corrections Issued NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 9/18/2025 Corrections Issued NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 9/23/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 10/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 10/21/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 10/21/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 10/28/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 10/28/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 11/6/2025 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 11/6/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/20/2025 Partial Approval CHRISTOPHER ROJAS
Insulation 12/3/2025 Corrections Issued JOAQUIN GREENOUGH
Insulation 12/8/2025 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 12/22/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/12/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 3/12/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/12/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 3/24/2026 Approved CHRISTOPHER ROJAS
Final 3/24/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/24/2026 Approved CHRISTOPHER ROJAS
Green Building Final 3/24/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 3/24/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 3/24/2026 Approved CHRISTOPHER ROJAS
Final 4/14/2026 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 4/14/2026 Approved KEVIN BERBERYAN