13001 W KAMLOOPS ST 91331
Certificate Information: 13001 W KAMLOOPS ST 91331
- Application / Permit
- 25010-20000-02570
- Plan Check / Job No.
- B25VN16309
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Proposed new 2-Story Accessory Dwelling Unit, all work per engineering
- Permit Issued
- Issued on 8/21/2025
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | RARES BODEA |
| Corrections Issued | 6/18/2025 | RARES BODEA |
| Quality Review Completed | 6/24/2025 | STEVEN KIM |
| Applicant returned to address corrections | 7/28/2025 | RARES BODEA |
| Plan Check Approved | 8/11/2025 | RARES BODEA |
| Issued | 8/21/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | JAVIER RAMOS JR |
| CofO Issued | 6/2/2026 | RUBEN SALAS |
| Permit Finaled | 6/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/18/2025 | WALTER RAMIREZ |
| Address approval | Cleared | 6/23/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 6/23/2025 | DERRICK MAGEE |
| ZI | Cleared | 6/25/2025 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 7/10/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/10/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 9/10/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 9/10/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/10/2025 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 9/18/2025 | No Access for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/19/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 9/19/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 10/15/2025 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 10/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 10/15/2025 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 10/20/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/30/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 10/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 10/30/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/5/2025 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 11/5/2025 | Approved | MICHEL ABAJAN |
| Insulation | 11/7/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/19/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/21/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/21/2025 | Approved | MICHEL ABAJAN |
| Sewer | 2/2/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/6/2026 | Approved | MICHEL ABAJAN |
| Final | 3/6/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 3/6/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/6/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/6/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 3/6/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 3/6/2026 | Approved | MICHEL ABAJAN |
| Final | 4/21/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 4/21/2026 | Approved | JAVIER RAMOS JR |