8129-8131 W GRAYSTONE ST 91040
Certificate Information: 8129-8131 W GRAYSTONE ST 91040
- Application / Permit
- 25010-20000-02516
- Plan Check / Job No.
- B25VN13151
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 37' X 44'-6" 1-STORY (2) ACCESSORY DWELLING UNITS PER GC66323(a)(2). NFPA 13D FIRE SPRINKLERS THROUGHOUT. LOT B
- Permit Issued
- Issued on 1/15/2026
- Issuing Office
- Current Status
- Issued on 1/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 5/29/2025 | HAYDON CHAN |
| Corrections Issued | 6/5/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 6/6/2025 | STEVEN KIM |
| Applicant returned to address corrections | 12/18/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 1/15/2026 | RAPHAEL ROSAS |
| Issued | 1/15/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2025 | LEE GUILBEAUX |
| Highway dedication | Cleared | 7/11/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/9/2025 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 10/20/2025 | ERNEST TSE |
| Miscellaneous | Cleared | 11/5/2025 | ASHLEY RODARTE |
| Senate Bill 9 | Cleared | 11/5/2025 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 11/7/2025 | GERMAN RODRIGUEZ MENDOZA |
| Roof/Waste drainage to street | Cleared | 11/17/2025 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 12/8/2025 | HAYDON CHAN |
| GPI Written Notices | Cleared | 12/18/2025 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 7/21/2026 |
Inspection Request History
| Underground Mechanical | 4/9/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 4/15/2026 | Approved | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 4/15/2026 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/25/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/10/2026 | Approved Pending GreenApproval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/10/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 7/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 7/10/2026 | Approved | NICHOLAS TROWBRIDGE |