8125-8127 W GRAYSTONE ST 91040

Certificate Information: 8125-8127 W GRAYSTONE ST 91040

Application / Permit
25010-20000-02515
Plan Check / Job No.
B25VN13151
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN NEW 39'-9" X 30'-6" 2-STORY DUPLEX per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING. LOT B
Permit Issued
Issued on 1/15/2026
Issuing Office
Current Status
Issued on 1/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/9/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 RAPHAEL ROSAS
Assigned to Zoning Architect 5/29/2025 HAYDON CHAN
Corrections Issued 6/5/2025 RAPHAEL ROSAS
Quality Review Completed 6/6/2025 STEVEN KIM
Applicant returned to address corrections 12/18/2025 RAPHAEL ROSAS
Plan Check Approved 1/15/2026 RAPHAEL ROSAS
Issued 1/15/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/24/2025 LEE GUILBEAUX
Highway dedication Cleared 7/11/2025 LEE GUILBEAUX
Permit Cleared 7/11/2025 LEE GUILBEAUX
Miscellaneous Cleared 9/26/2025 DURRE SHAMSI
Eng Process Fee Ord 176,300 Cleared 10/9/2025 LEE GUILBEAUX
Sewer availability Cleared 10/9/2025 LEE GUILBEAUX
Low Impact Development (LID) Cleared 10/20/2025 ERNEST TSE
Senate Bill 9 Cleared 11/3/2025 ASHLEY RODARTE
Miscellaneous Cleared 11/5/2025 ASHLEY RODARTE
Trees in Parkway Cleared 11/6/2025 RICHARD SANCHEZ
Grading Pre-Inspection Cleared 11/7/2025 MANUEL TEJADA
Roof/Waste drainage to street Cleared 11/17/2025 LEE GUILBEAUX
Zoning Plan Check Cleared 12/8/2025 HAYDON CHAN
GPI Written Notices Cleared 12/18/2025 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2026 Approved NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 4/15/2026 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/28/2026 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/28/2026 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2026 Partial Approval MATTHEW NELSON
Deputy Wood Construction 5/15/2026 Conditional Approval JOSE AVILA
Pre-Inspection 5/21/2026 Partial Inspection NICHOLAS TROWBRIDGE
Deputy Wood Construction 6/4/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 6/24/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/21/2026 Partial Approval NICHOLAS TROWBRIDGE