7406 1/2 N LEMP AVE 91605
Certificate Information: 7406 1/2 N LEMP AVE 91605
- Application / Permit
- 25010-20000-02505
- Plan Check / Job No.
- B25VN15799
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/30/2025
- Issuing Office
- Current Status
- CofO Issued on 6/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 6/7/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/17/2025 | APPLICANT |
| Plan Check Approved | 6/30/2025 | NAREG ATARIAN |
| Issued | 6/30/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 6/23/2026 | RUBEN SALAS |
| Permit Finaled | 6/23/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 6/30/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/30/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 8/27/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 9/10/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Approved | JOSE AVILA |
| Underground Mechanical | 9/19/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 10/22/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 10/23/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/30/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/30/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 11/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/12/2025 | Approved | JOSE AVILA |
| Green Building Rough | 11/12/2025 | Approved | JOSE AVILA |
| Insulation | 11/12/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 11/20/2025 | Approved | JOSE AVILA |
| Shower Pan | 11/20/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/3/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/20/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/20/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/20/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/21/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |