861 N ILIFF ST 90272
Certificate Information: 861 N ILIFF ST 90272
- Application / Permit
- 25010-20000-02490
- Plan Check / Job No.
- B25VN15735
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/1/2025
- Issuing Office
- Current Status
- Issued on 7/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | RAPHAEL ROSAS |
| Corrections Issued | 6/10/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 6/11/2025 | STEVEN KIM |
| Building Plans Picked Up | 6/13/2025 | APPLICANT |
| Plan Check Approved | 7/1/2025 | RAPHAEL ROSAS |
| Issued | 7/1/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2025 | CINDY QI |
| Permit | Cleared | 6/11/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/11/2025 | CINDY QI |
| Sewer availability | Cleared | 6/11/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 6/20/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/15/2025 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/24/2025 | Conditional Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 8/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 8/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/25/2025 | Partial Approval | JAYLIN GRAVITTE |
| ELECTRICAL-Rough | 10/6/2025 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/8/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Special/Order Compliance | 10/8/2025 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 10/9/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 10/31/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 11/3/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/3/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/14/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 11/26/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 11/26/2025 | Partial Approval | RUBEN RIVAS |
| Sewer | 1/13/2026 | Approved | DANIEL VERA |
| Gas Test | 3/4/2026 | Approved | MICHAEL ALLEN |