11618-11620 W SATICOY ST 91605

Certificate Information: 11618-11620 W SATICOY ST 91605

Application / Permit
25010-20000-02474
Plan Check / Job No.
B25VN15624
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. PROPOSED SINGLE FAMILY DWELLING PER SB9 TWO UNIT DEVELOPMENT WITH ATTACHED 2ND STORY ACCESSORY DWELLING UNIT PER STATE LAW GC 66323(a)(1) NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 10/26/2025
Issuing Office
Current Status
Issued on 10/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/2/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 JAD BASMA
Assigned to Zoning Architect 6/5/2025 MANUEL ZAVALETA
Corrections Issued 6/7/2025 JAD BASMA
Quality Review Completed 6/23/2025 HERNAN ARREOLA
Applicant returned to address corrections 9/18/2025 JAD BASMA
Applicant returned to address corrections 10/3/2025 JAD BASMA
Plan Check Approved 10/8/2025 JAD BASMA
Issued 10/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/13/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/13/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/13/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/22/2025 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 9/9/2025 LEE GUILBEAUX
Sewer availability Cleared 9/9/2025 LEE GUILBEAUX
Senate Bill 9 Cleared 9/25/2025 ALEX VELA
Zoning Plan Check Cleared 10/3/2025 Fernando Flores

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/10/2025 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 12/17/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/17/2025 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 12/18/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 1/15/2026 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 1/15/2026 Not Ready for Inspection JAVIER RAMOS JR