15433 W LEMAC ST 91406
Certificate Information: 15433 W LEMAC ST 91406
- Application / Permit
- 25010-20000-02443
- Plan Check / Job No.
- B25VN15431
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 24' X 34' detached two story accessory dwelling unit PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/20/2025
- Issuing Office
- Current Status
- CofO Issued on 6/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | JONATHAN PLATERO |
| Corrections Issued | 7/2/2025 | JONATHAN PLATERO |
| Quality Review Completed | 7/9/2025 | MICHAEL PEREZ |
| Applicant returned to address corrections | 9/9/2025 | JONATHAN PLATERO |
| Plan Check Approved | 10/16/2025 | JONATHAN PLATERO |
| Issued | 10/20/2025 | APPLICANT |
| CofO in Progress | 5/12/2026 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/5/2026 | RUBEN SALAS |
| Permit Finaled | 6/5/2026 | RUBEN SALAS |
| CofO Issued | 6/5/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/23/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 8/29/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 10/2/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Working Hands Builders Inc; Lic. No.: 1059742-B | , |
| Contractor | Z And J Manufacturing Group Inc; Lic. No.: 1059742-B | , |
| Engineer | Deihimi,, Amir; Lic. No.: C78194 | 201 E SANDPOINTE AVE STE 400 SANTA ANA, CA 92707 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/2/2025 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/4/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 12/22/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/21/2026 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/21/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/21/2026 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 1/26/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/27/2026 | Approved | VINCENT HANLEY |
| Insulation | 2/25/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/25/2026 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/3/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 3/3/2026 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/4/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/5/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/9/2026 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/24/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/24/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/24/2026 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 4/24/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/24/2026 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 4/24/2026 | Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 4/24/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/28/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 5/6/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | OGANES TARAKHCHYAN |