7113 N NATICK AVE 91405

Certificate Information: 7113 N NATICK AVE 91405

Application / Permit
25010-20000-02421
Plan Check / Job No.
B25VN15336
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan* New 2-story detached ADU per LAMC12.22 A.33(b)(1)
Permit Issued
Issued on 10/14/2025
Issuing Office
Current Status
Issued on 10/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 MATTHEW TORRES
Corrections Issued 6/7/2025 MATTHEW TORRES
Quality Review Completed 6/23/2025 HERNAN ARREOLA
Applicant returned to address corrections 7/8/2025 MATTHEW TORRES
Applicant returned to address corrections 7/14/2025 MATTHEW TORRES
Plan Check Approved 7/24/2025 MATTHEW TORRES
Issued 10/14/2025 APPLICANT
Permit Closed-Status Void 3/31/2026 VINCENT HANLEY
Re-Activate Permit 4/6/2026 VINCENT HANLEY

Permit Application Clearance Information

Address approval Cleared 6/13/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/13/2025 SAFA JAVANMARDI
Construction near power lines Cleared 6/18/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/24/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/25/2025 SAFA JAVANMARDI

Contact Information

Contractor Gp4 Construction; Lic. No.: 941647-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/17/2025 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 10/21/2025 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/21/2025 Approved RYAN SALAZAR
Deputy Wood Construction 11/10/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 1/30/2026 Corrections Issued VINCENT HANLEY
Green Building Rough 1/30/2026 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 1/30/2026 Not Ready for Inspection VINCENT HANLEY
Deputy Wood Construction 2/2/2026 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/11/2026 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 2/11/2026 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 3/13/2026 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 3/13/2026 Approved VINCENT HANLEY
Green Building Rough 3/13/2026 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 3/13/2026 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 3/13/2026 Corrections Issued VINCENT HANLEY
Verify Sprinkler Sign Off 3/13/2026 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 3/19/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Approved VINCENT HANLEY
Green Building Rough 3/19/2026 Approved VINCENT HANLEY
HVAC-Rough 3/19/2026 Approved VINCENT HANLEY
PLUMBING-Rough 3/19/2026 Approved VINCENT HANLEY
Insulation 3/25/2026 Corrections Issued GAREN HAYRAPETYAN
Drywall Nailing 3/31/2026 Not Ready for Inspection VINCENT HANLEY
Insulation 3/31/2026 Approved VINCENT HANLEY
Shower Pan 3/31/2026 Not Ready for Inspection VINCENT HANLEY
Drywall Nailing 4/7/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/7/2026 Approved VINCENT HANLEY
Shower Pan 4/7/2026 Approved VINCENT HANLEY
Sewer 6/1/2026 Approved VINCENT HANLEY
Underground Mechanical 6/1/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/4/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 6/4/2026 Approved VINCENT HANLEY
Final 6/4/2026 Corrections Issued VINCENT HANLEY
Green Building Final 6/4/2026 Approved VINCENT HANLEY
PLUMBING-Final 6/4/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/4/2026 SGSOV Not Required VINCENT HANLEY
Service/Power Release 6/4/2026 Approved VINCENT HANLEY
Smoke Detectors 6/4/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 6/4/2026 Not Ready for Inspection VINCENT HANLEY