6453 N AMIGO AVE 91335
Certificate Information: 6453 N AMIGO AVE 91335
- Application / Permit
- 25010-20000-02401
- Plan Check / Job No.
- B25VN15242
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24' X 22' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/2/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | SELLA BENYAMIN |
| Corrections Issued | 6/9/2025 | SELLA BENYAMIN |
| Quality Review Completed | 6/9/2025 | STEVEN KIM |
| Building Plans Picked Up | 6/10/2025 | APPLICANT |
| Plan Check Approved | 7/2/2025 | SELLA BENYAMIN |
| Issued | 7/2/2025 | APPLICANT |
| CofO in Progress | 4/27/2026 | JON MCHUGH |
| No Progress | 5/5/2026 | SEAN WIRCH |
| CofO in Progress | 5/5/2026 | SEAN WIRCH |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/11/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/11/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 6/18/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/29/2025 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 8/1/2025 | Corrections Issued | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 8/22/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 8/22/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Partial Approval | MORRIS JACKSON |
| HVAC-Rough | 9/10/2025 | Approved | MORRIS JACKSON |
| Insulation | 10/20/2025 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | JON MCHUGH |
| Green Building Rough | 10/30/2025 | Approved | JON MCHUGH |
| Insulation | 10/30/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/30/2025 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 10/30/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 11/3/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/19/2025 | Approved | JON MCHUGH |
| Shower Pan | 11/19/2025 | Approved | JON MCHUGH |
| Gas Test | 2/19/2026 | Approved | JON MCHUGH |
| HVAC-Final | 3/6/2026 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 3/11/2026 | Approved | JON MCHUGH |
| HVAC-Final | 3/11/2026 | Approved | JON MCHUGH |
| PLUMBING-Final | 3/11/2026 | Approved | JON MCHUGH |
| Final | 4/27/2026 | OK to Issue CofO | JON MCHUGH |
| Footing/Foundation/Slab | 4/27/2026 | Approved | JON MCHUGH |
| Green Building Final | 4/27/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 4/27/2026 | Approved | JON MCHUGH |