10010 N WHITAKER AVE 91343

Certificate Information: 10010 N WHITAKER AVE 91343

Application / Permit
25010-20000-02399
Plan Check / Job No.
B25VN15230
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan New detached ADU at the rear of the property per LAMC 12.22 A.33(b)(1)3. All work per engineer.
Permit Issued
Issued on 2/19/2026
Issuing Office
Current Status
Issued on 2/19/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Plan Check Engineer 8/22/2025 MINA HABILI
Corrections Issued 8/25/2025 MINA HABILI
Plan Check Approved 1/23/2026 NAREG ATARIAN
Issued 2/19/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/24/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/24/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/2/2025 BIAINA HARITUNIAN
Sewer availability Cleared 12/2/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 12/5/2025 GEVORK KARAPETYAN
Grading Pre-Inspection Cleared 12/11/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 7270 HILLSIDE AVE   APT 306    LOS ANGELES, CA 90046

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/22/2026 Approved WAYNE REGESTER
Excavation/Setback/Form/Re-Bar 4/28/2026 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 4/28/2026 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Approved DAVID MATSON
PLUMBING-Rough 5/12/2026 Corrections Issued DAVID MATSON
PLUMBING-Rough 5/18/2026 Approved KEVIN BERBERYAN
Sewer 5/18/2026 Approved KEVIN BERBERYAN