9553 N GLADBECK AVE 91324
Certificate Information: 9553 N GLADBECK AVE 91324
- Application / Permit
- 25010-20000-02313
- Plan Check / Job No.
- B25VN14753
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(b)(1) AND 2ND FLOOR BALCONY PER ENGINEERING
- Permit Issued
- Issued on 7/12/2025
- Issuing Office
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | ALFRED RAMIREZ |
| Corrections Issued | 6/16/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 6/17/2025 | STEVEN KIM |
| Plan Check Approved | 7/12/2025 | ALFRED RAMIREZ |
| Issued | 7/12/2025 | APPLICANT |
| CofO in Progress | 3/27/2026 | DAVID SCANTLIN |
| CofO in Progress | 4/7/2026 | JOHN JANSON |
| Permit Finaled | 4/8/2026 | JOHN JANSON |
| Permit Finaled | 4/8/2026 | JOHN JANSON |
| CofO Issued | 4/8/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2025 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 6/20/2025 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2025 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 6/24/2025 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 6/27/2025 | YINGSHI HUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/21/2025 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Rough | 9/2/2025 | Partial Approval | KRISTEN CAUSEY |
| Sewer | 9/2/2025 | Approved | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 9/9/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | KRISTEN CAUSEY |
| Deputy Wood Construction | 9/24/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Corrections Issued | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 10/7/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 10/7/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 10/7/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/16/2025 | Partial Approval | KRISTEN CAUSEY |
| Shower Pan | 10/16/2025 | Approved | KRISTEN CAUSEY |
| Insulation | 10/20/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 10/24/2025 | Conditional Approval | KRISTEN CAUSEY |
| Drywall Nailing | 10/24/2025 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 10/24/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/13/2025 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 3/4/2026 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/16/2026 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/23/2026 | Approved | DAVID SCANTLIN |
| Final | 3/23/2026 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 3/23/2026 | Approved | DAVID SCANTLIN |
| Green Building Final | 3/23/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2026 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 3/23/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 3/23/2026 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/23/2026 | Approved | DAVID SCANTLIN |
| Final | 3/26/2026 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 3/26/2026 | Approved | DAVID SCANTLIN |
| Service/Power Release | 3/26/2026 | Approved | DAVID SCANTLIN |