14836 W LASSEN ST 91345
Certificate Information: 14836 W LASSEN ST 91345
- Application / Permit
- 25010-20000-02234
- Plan Check / Job No.
- B25VN14394
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23'-9" X 33'-6" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
- Permit Issued
- Issued on 7/23/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 5/29/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/30/2025 | APPLICANT |
| Plan Check Approved | 6/25/2025 | OMAR GARNICA |
| Plan Check Approved | 6/25/2025 | OMAR GARNICA |
| Issued | 7/23/2025 | APPLICANT |
| CofO in Progress | 2/12/2026 | JENNIFER RABUCHIN |
| CofO Issued | 3/24/2026 | RUBEN SALAS |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/12/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/12/2025 | RYAN CASTRO |
Contact Information
| Contractor | Gt Remodeling Inc; Lic. No.: 1091310-B | 15250 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/15/2025 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 8/15/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 8/15/2025 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Reinforced Concrete Frame | 8/28/2025 | Partial Inspection | JENNIFER RABUCHIN |
| Reinforced Masonry Frame | 8/28/2025 | Partial Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 9/2/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 10/1/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/17/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/17/2025 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/17/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/30/2025 | Approved | CHRISTOPHER MORFIN |
| Drywall Nailing | 11/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 12/3/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | JENNIFER RABUCHIN |
| Final | 1/20/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/20/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 1/20/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/20/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 1/20/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 2/6/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/13/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/13/2026 | Approved | JENNIFER RABUCHIN |