14836 W LASSEN ST 91345

Certificate Information: 14836 W LASSEN ST 91345

Application / Permit
25010-20000-02234
Plan Check / Job No.
B25VN14394
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-9" X 33'-6" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
Permit Issued
Issued on 7/23/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 ARTIN ZARUKIAN
Corrections Issued 5/29/2025 ARTIN ZARUKIAN
Building Plans Picked Up 5/30/2025 APPLICANT
Plan Check Approved 6/25/2025 OMAR GARNICA
Plan Check Approved 6/25/2025 OMAR GARNICA
Issued 7/23/2025 APPLICANT
CofO in Progress 2/12/2026 JENNIFER RABUCHIN
CofO Issued 3/24/2026 RUBEN SALAS
Permit Finaled 3/24/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/12/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/12/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 6/12/2025 RYAN CASTRO
Sewer availability Cleared 6/12/2025 RYAN CASTRO

Contact Information

Contractor Gt Remodeling Inc; Lic. No.: 1091310-B 15250 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/15/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/15/2025 Partial Approval JENNIFER RABUCHIN
Sewer 8/15/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 8/15/2025 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 8/28/2025 Corrections Issued JENNIFER RABUCHIN
Reinforced Concrete Frame 8/28/2025 Partial Inspection JENNIFER RABUCHIN
Reinforced Masonry Frame 8/28/2025 Partial Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 9/2/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 10/1/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/17/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 10/17/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved JENNIFER RABUCHIN
Green Building Rough 10/17/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 10/17/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 10/17/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/17/2025 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 10/17/2025 Approved JENNIFER RABUCHIN
Insulation 10/30/2025 Approved CHRISTOPHER MORFIN
Drywall Nailing 11/7/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 12/3/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/20/2026 Approved JENNIFER RABUCHIN
Final 1/20/2026 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/20/2026 Approved JENNIFER RABUCHIN
Green Building Final 1/20/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 1/20/2026 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 1/20/2026 Approved JENNIFER RABUCHIN
Final 2/6/2026 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 2/6/2026 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 2/13/2026 Approved JENNIFER RABUCHIN
Final 2/13/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/13/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/13/2026 Approved JENNIFER RABUCHIN
Service/Power Release 2/13/2026 Approved JENNIFER RABUCHIN