10433 W VALLEY SPRING LANE 91602

Certificate Information: 10433 W VALLEY SPRING LANE 91602

Application / Permit
25010-20000-02198
Plan Check / Job No.
B25VN14205
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING UNIT WITH 2ND FLOOR DECK, ATTACHED FRONT TRELLIS PORCH AND ATTACHED 2-CAR GARAGE PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 8/12/2025
Issuing Office
Current Status
CofO in Progress on 6/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2025 APPLICANT
Assigned to Zoning Architect 5/22/2025 KRISTEL MARQUEZ
Assigned to Plan Check Engineer 5/29/2025 ALFRED RAMIREZ
Corrections Issued 6/1/2025 ALFRED RAMIREZ
Quality Review Completed 6/3/2025 STEVEN KIM
Building Plans Picked Up 6/4/2025 APPLICANT
Plan Check Approved 8/12/2025 ALFRED RAMIREZ
Issued 8/12/2025 APPLICANT
CofO in Progress 6/29/2026 JAVIER RAMOS JR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2025 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 6/12/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 6/12/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 6/23/2025 PATRICK PEREZ
ZI Cleared 7/11/2025 JASON CHAN
Trees in Parkway Cleared 7/14/2025 MIGUEL ORNELAS
Permit Cleared 7/21/2025 RYAN CASTRO
Sewer availability Cleared 7/28/2025 SAFA JAVANMARDI
Zoning Plan Check Cleared 8/11/2025 KRISTEL MARQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/10/2025 Partial Approval JAVIER RAMOS JR
Deputy Reinf. Concrete 9/15/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/15/2025 Partial Approval JAVIER RAMOS JR
Deputy Reinf. Concrete 9/16/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/19/2025 Partial Approval JAVIER RAMOS JR
Deputy Steel/Welding 9/23/2025 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 10/31/2025 Approved JAVIER RAMOS JR
HVAC-Rough 10/31/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/31/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 11/12/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 11/12/2025 Approved JAVIER RAMOS JR
Wood Frame 11/12/2025 Partial Inspection JAVIER RAMOS JR
Shower Pan 11/13/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 11/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Wood Frame 11/17/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/20/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/10/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/15/2025 Approved JAVIER RAMOS JR
Green Building Rough 12/15/2025 Approved JAVIER RAMOS JR
Insulation 12/15/2025 Approved JAVIER RAMOS JR
Drywall Nailing 12/18/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/14/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 5/14/2026 Approved JAVIER RAMOS JR
Green Building Final 5/15/2026 Approved JAVIER RAMOS JR
HVAC-Final 5/15/2026 Approved JAVIER RAMOS JR
Service/Power Release 5/15/2026 Approved JAVIER RAMOS JR
Final 6/23/2026 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/23/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/23/2026 Approved JAVIER RAMOS JR
Final 6/26/2026 OK to Issue CofO JAVIER RAMOS JR