8154 N WHITE OAK AVE 91325
Certificate Information: 8154 N WHITE OAK AVE 91325
- Application / Permit
- 25010-20000-02196
- Plan Check / Job No.
- B25VN14195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW DETACHED 1-STORY 2ND DWELLING UNIT PER SB9-TWO UNIT DEVELOPMENT PER WFPP. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 12/19/2025
- Issuing Office
- Current Status
- Issued on 12/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | ALFRED RAMIREZ |
| Assigned to Zoning Architect | 6/5/2025 | LY CHEA |
| Corrections Issued | 6/7/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 6/17/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/10/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 12/18/2025 | ALFRED RAMIREZ |
| Issued | 12/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2025 | BIAINA HARITUNIAN |
| Highway dedication | Cleared | 6/21/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/24/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/9/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/23/2025 | GEVORK KARAPETYAN |
| Hydrant and Access approval | Cleared | 9/25/2025 | KURT CORRAL |
| Senate Bill 9 | Cleared | 10/9/2025 | FIPE LEILUA |
| Zoning Plan Check | Cleared | 12/8/2025 | LY CHEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/5/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Pre-Inspection | 2/5/2026 | Partial Inspection | GAREN HAYRAPETYAN |
| Underground Mechanical | 2/5/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/18/2026 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/14/2026 | Approved | KIRK SANDERS |
| Sewer | 4/20/2026 | Approved | MICHAEL CORTEZ |
| Underground Mechanical | 4/20/2026 | Partial Approval | MICHAEL CORTEZ |